09-04-2017 VF-C Weekly Meeting

Attendees:

 Ritusood,han yanan,maopeng,jinhua,Yan Yang,Victor Gao,Chengli,Yunlong

Agenda:

  1. summarize the recent work and give some feedback to the team

  2. the job that need to finish in this week

  3. other discussion

Minutes:

First topic

  1. Yan gives some information that got from last week's meeting
    M4 date and all subsequent milestones for Amsterdam have been postponed by 2 weeks for a new release date of Nov 16
    Discussion with SDC team and A&AI team.

  2. Maopeng feedbacks the latest status and the discussion result with SDC team.
    For VNF package format, have reached a basic consensus
    NSD and VNFD, SDC team are under developing 
    VoLTE E2E service design. SDC showed the whole process in last discussion meeting

  3. Victor introduced the A&AI schema changes work progress from VF-C perspective
    The schema changes have approved by A&AI team and the validation is still have some problems.other team like esr also has the similar validation problem.
    Victor are fixing these problem and follow other team's validation progress.
    Yan suggests victor share the information about NS with Ritusood by email.


Second topic

  1. Yan introduced the work that need to be finished in this week.
    Integration work with OOM should be finished in September 8th.
    Team are working on the docker image buliding.
    VF-C team have got help from Shashank and Mandeep team.

  2. Jinhua has summarized the work progress for docker image building.
    There is only remaining one issue that push the image to nexus about vfc-nfvo-lcm and vfc-gvnfm-vnflcm.
    When the work is done,other components can follow these scripts.

  3. Yan introduce the documentation requirements and solicit volunteers.
    Noboday feedback.If any one want to take on this job can contact Yan by email.

  4. Yan mentioned the marketing materials
    Each project should provide some materials, inculding functonalities,api and other description.Should confirm more details about the requirements.

  5. Chendli shared the information that each team should provide two remotely accessary accountsk for Developer Lab Access



Action:

  1. Maopeng will share meeting recording link with VF-C team which includes the Volte E2E service design demo.

  2. Maopeng will share the VNF CSAR format with VNF vendor that has been supported in SDC team in R1.

  3. Weitao will follow the A&AI schema validation and provide the schema changes and APIs within the team and Ritusood.

  4. Jinhua will fix the remaining issue about the docker image building for vfc-nfvo-lcm and  vfc-gvnfm-vnflcm.

  5. Jinhua will send email to VF-C team to introduce how to write the related scripts about building docker image and other components can refer this as an instruction.

  6. Yan will follow the document guildlines and make sure the requirements and call for volunteers

  7. Yan will confirm the marketing requirement for each project.

  8. Yan will copy the M4 milestone checklist to VF-C wiki page.

  9. Yan will  confirm two people that have the Developer Lab Access right.