START RECORDING AntiTrust Message

10min

CSIT review

@Morgan Richomme

@Lasse Kaihlavirta

Currently few failing jobs - please direct attention to getting these tests functioning correctly.

Useless CSIT test elimination

20 mins

El-Alto Release

@Former user (Deleted)

@Jason Hunt

@Paweł Pawlak

@Brian Freeman

@Morgan Richomme

Project Status in El-Alto Release

10min

Frankfurt Planning - Focus on the subcommittees 

@David McBride

@Paweł Pawlak

@Alla.Goldner

@Stephen terrill

@Hui Deng  @Andy Mayer

@Pamela Dragosh

  • Frankfurt schedule review

  • Frankfurt Release Requirements

    • Requirements freeze - Sept 27

    • 41/44 requirements with corresponding JIRA issues in REQ

  • oparent/AAF/CCSDK/Portal/SDC SDK released jar artifacts - need a deliverable milestone (M3? before M4) @David McBride

  • SECCOM recommendations for Frankfurt various software platforms upgrades 

    • Programming languages

    • Docker, Kubernetes

    • Alpine

    • Databases

  • Python2 to python3 upgrade is a requirement for Frankfurt - REQ-174: Remove dependencies on Python2Done 

10min

ONAP deliverables outside the release

@cl664y@att.com

The following activities are implemented outside the normal cycles by the project teams:

  1.  Completion of Self-Serve releases (Jessica Wagantall )

  2.  Dockerhub migration (Cristina Pauna )

  3.  Move OOM Helm Charts ownership to project team (Mike Elliott )

  4.  Ingress Controllers (Krzysztof Opasiak)

15min

DockerHub Migration update

@cristinapauna

Cross project dependencies

onap-discuss message: https://lists.onap.org/g/onap-discuss/topic/dockerhub_migration_and/34447632?p=,,,20,0,0,0::recentpostdate%2Fsticky,,,20,2,0,34447632

wiki: Migration to DockerHub

From TSC Chat:

"The proposal is to generate the release tag only by the release Jenkins job (now it's also generated by the staging job). I will not be able to join the PTL meeting next week, so I will go to the OOM and CSIT meetings next Wednsday to discuss it. I will come back next week at the TSC meeting with the result."

5min

LF Infrastructure/Rel process

@Jessica Gonzalez

@Kenny Paul (Deactivated)

10 mins

Remaining Action Items

@Former user (Deleted)

PTL Weekly ONAP12, Mon UTC 13:00

15min

ONAP release cadence 

@Chaker Al-Hakim

Explore release process cadence

Zoom Chat Log 

06:13:48 From Guangrong FU : Some of the disabled CSIT jobs are still useful (although they have not been running for a long time), who should we report that to?
06:14:11 From Lasse Kaihlavirta (Samsung) : You should fix them and restore them :)
06:14:16 From Lasse Kaihlavirta (Samsung) : no need to report them to anyone else
06:14:24 From Guangrong FU : OK, gotcha.
06:14:26 From Guangrong FU : Thx.
06:28:41 From Guangrong FU : I'm sorry to disturb. But I do have a question for El Alto. Catherine email me, asking me to update the release notes. But the fact is that I pushed the latest release notes to the master branch a couple of days ago. But the changes seem not to be reflected on readthedocs. Does anyone have any idea?
06:34:05 From David McBride : https://lf-onap.atlassian.net/wiki/display/DW/El+Alto+Release+Key+Updates
06:37:44 From Brian Freeman (AT&T) : cherry pick from master to elalto
06:37:46 From Guangrong FU : OK. Thanks.
06:37:48 From Brian Freeman (AT&T) : for documentation updates
06:49:41 From Eric Debeau : https://docs.onap.org/en/dublin/release/index.html
07:04:30 From Sofia Wallin : I need to leave. but I encourage everyone with open documentation issues or tasks to join the doc call on Thursday.
07:15:59 From Dan Timoney : CCSDK does not agree to deliver a Frankfurt drop at M3
07:17:14 From Dan Timoney : (Problem is there wont be anyone around in mid-late Dec to do fixes … so better to target early Jan for first code drop)
07:19:48 From Brian Freeman (AT&T) : lets get feedback from each client of an SDK and what date makes sense to folks. we can have two dates or we may find that portal and sdc sdk receivers have the same schedule and are fine with a early january delivery of the updated sdk's but not late Feb



Action Items 

@Former user (Deleted) update feedback table on El Alto status page
@Sofia Wallin investigate https://lists.onap.org/g/onap-release/message/1422 and report back whether still relevant
@David McBride follow up with @Former user (Deleted) regarding RN overview page for El Alto (see Dublin)
@David McBride follow up with @Pierre Close regarding license scan results