PTL 2019-07-29

PTL 2019-07-29

zoom bridge: https://zoom.us/j/283628617

Duration 60 minutes

Duration

Agenda Item

Requested by

Notes / Links

Duration

Agenda Item

Requested by

Notes / Links

START RECORDING

 

Review agenda 

 

Add any other topics

15 mins

El-Alto Release

@Former user (Deleted)

All containers for Early Drop due TODAY. If not what's your plan? Descoped or still possible later this week?

M1 planning - Project Status in El-Alto Release Insufficient Progress by: Documentation, Integration, UUI, CLI - What is blocking this activity?

Platform Maturity - El-Alto Release Platform Maturity missing Holmes, ExtAPI, Music, CLI, Integration, UUI, VNFSDK

Current High/Highest (including 1 Blocker (SDC) and 8 Integration issues)- Defect Status for El Alto

 

SDC CLM job

@Ofir Sonsino

#Action - @Ofir Sonsino will continue to discuss with @Jessica Gonzalez about the possibility to create several Jenkins Jobs

 

Sonar scans and goals

 

@Former user (Deleted)

Below goal - PTL to provide an improvement plan

Module

Without jScript

With jScript

ccsdk-dashboard

66.6

18.4 - what can be achievable? 25%? Dan T. to confirm

aaf-authz

40

40 -> 50%?

sdc master

48.3

48.4 → 55%?

ccsdk-sli-adaptors

49.4

49.3 → 55%?

policy-engine

57.7

49.7 → 55%?

ccsdk-sli-northbound

50.8

49.9 → 55%?

aai-graphadmin

53.1

53.1 -> to be reviewed based on Jimmy's inputs

aai-data-router

53.2

53.2 -> to be reviewed based on Jimmy's inputs

aai-schema-service

53.4

53.4 -> to be reviewed based on Jimmy's inputs

ccsdk-sli-core

53.4

53.4 → 55%?

sdc-jtosca dublin

53.7

53.7 → 55%?

aai-sparky-be

53.8

53.8 -> to be reviewed based on Jimmy's inputs

sndc-northbound

54.5

54.5 → 55%?

 

M2 milestone review

@Former user (Deleted)

M2/M3 

  • API docs complete

  • Data Models (e.g, JSON, YANG, Swagger, etc.) shared with Modeling/Community

  • Architecture Review complete (if required)

  • No Gerrit requests older than 36 hrs.

  • Provide docker to integration testing for El Alto Early Drop

  • OOM port list update

  • Fix any Integration blocker - Daily status updates on integration blockers, Highest/High issues

  • Review and plan resolution of any License scan, security issues

  • Begin release notes for Early Drop

  • Update Risk Register

15min

Change default expiration time for AAF Certs

@Paweł Pawlak @Jonathan Gathman @Amy Zwarico

The goal is to review with the community possible options: one of them is to extend it to 5 years.

 

Suggestion: automate certificate renewal and move to shorter expiry time. Over 5 year period, people could easily forget how to do it and be out of practise at the next renewal, perhaps resulting in another emergency release to fix.

See documentation on the config/cert process

5min

OJSIs status update

@Paweł Pawlak @Krzysztof Opasiak

Review of the status with special focus on OJSI's jiras with CVE assigned.

5min

CII Badging update

@Paweł Pawlak @Amy Zwarico @Tony Hansen

Confirmation of Silver level for El Alto = the one for Dublin.

Review of the status of CII Badging answers with special focus on updates related to:

  • Crypto question

  • LF Projects Code of Conduct

  • OJSIs with CVEs and respecting 60 days period (deadline is 27th of July)

  • PTLs elections and need to change project CII Badging editors

5min

Nexus-IQ vs. Whitesoftware benchmarking

@Paweł Pawlak @Amy Zwarico

Sharing first thoughts  for CCSDK benchmarking with both tools. 

5min

How can we better support?

@Paweł Pawlak @Amy Zwarico

We would like to collect from the community list of topics that are valuable for the teams that we could bring during our next F2F meeting in Antwerp.

10min

 

@Former user (Deleted)

Action Items review: PTL Weekly Meeting #ptl

 

DCAE and global-jjb migration issues

@Vijay Kumar

DCAE jobs invoking docker on gerrit-maven job failing on centos node related to permission issue.  Seeking input from any other team if they had been successful in generating docker containers on centos node.

 

Up coming events

 

ONS Joint Sub committee meetings - Sept 26&27 Antwerp

Zoom Chat Log 

07:14:10 From Keong : who is Integration team PTL now?
07:17:33 From Catherine Lefèvre : PTL election is in progress
07:17:42 From Catherine Lefèvre : Brian is the interim Integration person
08:01:17 From Jonathan Gathman : Doc I did: Application Config & Cert Documentation (Temporary)
08:02:19 From Keong : @jonathan if the certs are automated why move to 5 year expiry?
08:06:32 From Amy Zwarico : Keong: I suggested changing the expiration to 5 years in response to the cert issues that occured in Dublin testing. If all projects integrate automated certificate provisioning, there is no need to increase the expiration period.

Action Items