Date
Sep 9, 2021
Attendees
@Kenny Paul, @Lincoln Lavoie, @Stephen Gooch, @Bob Monkman (Deactivated) , @steve ira
Discussion items
Contract with UNH signed
PO for servers needed to be resubmitted by Intel - delay of a few days
HW will be delivered end of Sept / early Oct time frame
VPN access to the servers will be configured by UNH
Need a local jump station with access to the local BMCs
Wind River will do OS provisioning once jump host is configured
Bare metal will be installed with Wind River's centos as is the case now
TOR - will be using 48 port Cisco 9000s
moves the lab from 20G throughput to 100G throughput
Passwds will be shared between Lincoln and Stephen at least for launch -
Wind River needs Admin access to the servers and BMCs
Integration leads need OS admin
Users just get user access
No existing Intel Lab user accounts will be brought forward
New accounts will need to be requested via https://jira.onap.org/projects/OPENLABS
Jira will be monitored by both Wind River and UNH
Intel lab will be decommissioned following Istanbul sign-off
Local caching in UNH may be a future conversation from a performance standpoint
Billing starts September beginning with rack/switch config