SO Weekly Meeting 2020-12-02
Agenda Topics:
Project Status in Guilin Release
Guilin Impact View per Component
Guilin release - non-functional requirements proposed list
New:
Guilin Exception Request for SO
Service Orchestrator Guilin Release M4
RC2 Criteria
Blocking issues :
License scan issues:
SO-3292: Issue with the license scan on the JBoss lib used in SOClosed
https://gerrit.onap.org/r/c/oom/+/111328
SO committer promotion:
Way forward for Honolulu:
What went wrong:
Communication with OOM was not effective
OOM delays impacted SO feature delivery delays
• Master branch was not stable because a lot of features and Java 11 upgrade and certificate issues
• Some testing required additional OOM changes
• OOM best practices were not broadcasted to the feature teams
• Security best practices / guidance came out in the middle/late of development cycle
• Image release number changed multiple times during the Guilin release
What was good:
The team could come out of the difficult time and meet the target
Response time from SO team was really good
In the end the issues were are fixed a release was fix.
What can be improved:
Reduced code fragments (new projects on the gerrit) for build
Introduce the gating as part of the jenkins verification process (2 edged sword to deal with, work with the details).
Increase in auto verification
• OOM best practices / guidance should come earlier and documented