SO Weekly Meeting 2020-02-19

Topics:

SO passed M2/M3 

Release Planning: Frankfurt

Project Status in Frankfurt Release



Review 

ARC Service Orchestrator Component Description - Frankfurt

Code Freeze : 2nd March the final.



Requirements

M1 committed Requirement details

M4 preparedness Status

SO-2556

Migrate PNF PNP workflow to Building Blocks

Risk on completing by Feb, decision point API has dependency taht is not yet resolved.

Backup plan: The existing flow is intact and we will switch back to the existing code till the new changes are merged.

SO-2519

S3P - Improvements of Service Orchestrator

Need to revisit based on the bading demands

SO-1579

SO supports ETSI SOL005 Alignment of its interfaces with NFVO

Expected to finish code review by next week. Yet to start Module level testing.

SO-2432

Multi-domain Optical Network Service Orchestration Support in SO

This week expected the code review. Module level is in progress. So code is submitted for review.

SO-2427

SOL002 Adapter - supports EM-triggered VNF/VNFC Management

SO-2428 in progress. Use-case testing will probably be delayed post M4. 

SO-2404

SO Catalog Management Support

No risk, code by this week, testing to be completed. 

SO-2368

Support 5G slice orchestration

working on OOF integration part, FInal integration testing of OOF. This week the coding is targeted. Testing will contnue next week, have dependency on OOF.

SO-2281

SO support of Network Slicing Demo in Frankfurt

Demo will follow the same as above. Last week the demo has been addressed.

SO-2156

ETSI Alignment Support - SOL003 Adapter Enhancement for Frankfurt

No risk, testing in progress. WIth in 2 weeks. 

Support to HTTPs is not yet provided by the ETSI catalog manager, this is to be resolved either by the change the adapter or the api. The functional test is intact and the final decision on this will be taken by this week. Next week finish the testing.

SO-2087

AAI update for VNF improvements



SO-2086

SO Multicloud plugin to Multicloud improvements

Testing effort, will need to take it as per the need. Https call to the MC. dependency on the changes of the MC. 

Plan to complete this by next week.

SO-2046

support Java 11 upgrade

The initial analysis is done. the code is being done in a separate branch and testing is in progress for the vFW usecase.

Oparent should be 3.0.0

Java SDK should be the one from Integration team.

SO-2519

 TSC must have

SO code coverage after the migration to sonar cloud is 65% - PASS

SO/libs - In progress

Upgrade capabilities - In progress

Vulnerabilities fix - So/libs - In progress.



Issues open :

type key summary assignee reporter priority status resolution created updated due
Loading...
Refresh

 



Discussion:

  • ETSI based solution over the K8S for CNF orchestration - Byung and Fred

  • TSC Must haves SO-2519



Provide Upgrade Capabilities... SO-2520

Under Analysis



SECCOM Perform Software Composition Analysis - Vulnerability tables

https://lf-onap.atlassian.net/wiki/pages/viewpage.action?pageId=16089452

https://lf-onap.atlassian.net/wiki/display/DW/Proposal%3A+Remediating+Known+Vulnerabilities+in+Third+Party+Packages




SECCOM Password removal from OOM HELM charts – This is being discussed with ATT team SO-2535


SECCOM HTTPS communication vs. HTTP (Integration with AAF) – This is due for further confirmation of the role of AAF in F and further releases.