[portal-platform] 06-26-2019 portal weekly meeting

[portal-platform] 06-26-2019 portal weekly meeting

Attendees:  

  @Lorraine A. Welch@Leimeng Shi,

Agenda:

 Today El Alto plans:

  1. Proposed fix for Apps_Users_Onboarding_Script.sql - will this reside in oom as oom_updates.sql; will the older version of Apps_Users_Onboarding_Script.sql still be run?

    1. Move  Apps_Users_Onboarding_Script.sql from Portal/Deliveries  to OOM directory ([oom.git] / kubernetes / portal / charts / portal-mariadb / resources / config / mariadb / )

    2. Sunder will disable the old  Apps_Users_Onboarding_Script.sql in the old image

  2. Raptor feature changes made for ENMT SDK need to be added to ONAP Portal SDK

  3. HIgh Jira Onboarding Apps - PORTAL-497

  4. Security gerrit reviews have to be completed; conflicts have to be resolved - Sunder's team

  5. Check documentation

  6. Testing - check with Sireesh

  7. Log improvement

  8. Need to review Jira tickets for El Alto to see which appropriate for next release - Lorraine will send out email stating at next week's meeting we will review all Jira tickets for El Alto.

  9. Is the VID issue PORTAL-555 a portal issue or a VID issue?

Older:

  1. request Sunder to review the open gerrit reviews; Sunder's team is going to review the gerrit commits and if good, we will merge

  2. Sireesh to update on his testcases; Sireesh is working on it

  3. Sireesh will ask Saravanan about his Angular changes and get back to us; we need to find his code, ng-app - how to trigger this page



Older issues:

  • PORTAL-330: Angular Upgrade to latest versionClosed - Deven and Saravanan started the userstories. - Action item - Manoop review and push to next release - update: still in progress

    • PORTAL-507: Develop SDK’s “sample usage page” using polymer web componentClosed - Saravavanan to explore the new screens to identify best screen to upgrade polymer. - update: still in progress

    • PORTAL-516: Review the challenges in software stack upgradeClosed - Deven upgrading the springboot - starting with os, common (might not be needed) overlay projects to load the system.properties file. - update: still in progress

      •  

        •  

          •  

            • all springboot dependancies were found and code is getting complied

              • properties files (19) put in one folder: [portal/sdk.git] / ecomp-sdk / epsdk-app-os / src / main / resources / 

            • hibernate update needed to be compatible with springboot 2.1.3 - might possibly use jpa

            • identify properties across app, where should they be put (should load at runtime) ; 2 ways to do it external configuration or property placeholder configuror 

              • app-os needs properties - need to combine from different file of different project - this will go in the resources section of app-os

              • in spring.xml there will be a property placeholder configuror section 

              • spring application json is the other way - looking at it

            • converting to springboot needs appl context has to be created from one class; discovering how to do this

            • annotations or xml (or both)

            • usually a java class to implement (starting point of springboot application ) application context - needs more info on this concept

            • will look at sample application to figure how configuration is stored

            • started a sample springboot app - Deven still working on this

    • PORTAL-508: Upgrade SDK’s home page using Angular+PolymerClosed - Saravanan was working on Angular and Polymer - update: still in progress

      • Last discussion was on to use Polymer or not - status??

      • Roles page -example is in Gitlab

      • Deven worked other projects this past week, will try and spend time this week on this - Deven not working this now

  • Robot scripts will be updated in Dublin - update: still in progress

    • @Sireesh Chintamani (Deactivated)  - adding new robot tests for Dublin release 

    • top menu change for 5G use cases, see if they broke the current robot test for top menu - code change was made in [portal.git] / deliveries / Apps_Users_OnBoarding_Script.sql therefore it is not used; fix for El Alto



  • Highest and High Defects:  







All portal bugs

key summary type created updated due assignee reporter priority status resolution
Loading...
Refresh

Dublin Release (May 2019)

  • M1 Release PlanningJan 24, 2019

  • M2 Functionality FreezeMar 21, 2019

  • M3 API/Data Model Freeze Mar 14, 2019

  • M4 Code Freeze Apr 4, 2019

  • RC0 Checklist Apr 25, 2019

  • RC1 Checklist May 9, 2019

  • RC2 Checklist May 23, 2019

  • Release Delivery Jun 13, 2019