Guilin Exception Request for CLAMP





Name

@ChrisC (acting for @Gervais-Martial Ngueko)



Milestone or Requirements Exception?

Requirement



Project or Requirement Name and JIRA





Milestones affected

N/A



Projects affected



N/A



Background description

The main containers with application have been updated but some dependencies are out of our control, moreover there is not enough CLAMP resources in this release to complete the work.

The CLAMP frontend use a small NGNIX container which is not base image, the ONAP base image was way too big for the purpose. the proposition would be to adopted this as a base image for NGNIX.



Schedule impact

N/A





Recovery plan



will postpone remaining items to next release, continuing phased approach



Milestone schedule change

N/A



Risk

Risk was provided, try to gather more resources for next release



Status



Decision