Guilin Exception Request for AAF

Guilin Exception Request for AAF





Name

@David McBride

Milestone or Requirements Exception?

Requirement

Project or Requirement Name and JIRA



Milestones affected

N/A



Projects affected

N/A



Background description

The AAF project is currently in maintenance mode and there are no resources for complying with these requirements.

Schedule impact

N/A



Recovery plan

There is no near-term mitigation possible.  Long-term, the AAF project should be archived and the needed functionality moved to other projects, or to a new project.



Milestone schedule change

N/A



Risk

The security issues represented by these requirements will continue to be a risk.

Status

Decision