September 12th to September 18th, 2017
Template:
What has your team achieved in past one week?
Block issues / help needed from the community
Review the list of defects identified by the Integration Team
Review the JIRA defects introduced by the Integration in order to ensure that these are visible as part of the Integration Dashboard
Review issues raised on "ONAP master branch Stabilization" and update the JIRA defects to be reflected as part of the Integration Dashboard
Review the JIRA defects to ensure the information are up-to-dated
Reference VNFs (vFW/vLB)
vFW and vLB work in the new developer lab
The test didn't include ONAP (only vFW and vLB/vDNS functions)
ONAP installation
Installed k8s cluster from skratch
Installed ONAP via OOM (APPC and SDNC have issues, possibly not related to the installation approach)
Discussed Heat vs. k8s approach: many teams seem to prefer Heat for R1, need to check possible dependencies on OOM
If Heat is confirmed as installation method for R1, is this the updated list of components that Heat should support (gating projects - MVP)?
AAI, APPC, CCSDK, CLAMP, DCAE GEN2, DMAAP, INTEGRATION, MSB, MULTIVIM, OOM, POLICY, PORTAL, SDNC, SDC, SO, VFC, VID
Release / O-Parent
Ongoing help to the community on versioning/release process, CSIT environment setup, O-Parent implementation, etc.
Bootstrap
The Unit tests and library scripts have been reviewed to ensure that are covering latest changes on the projects.
vCPE
All design cases confirm that they are on track to meet M4 (vCPE Design and Test Cases)
Service model revised to simplify SO workflow designs. Robot will be used extensively to orchestrate decomposed services in vCPE.
Dan Timony confirmed that he will work on the required Yang and DGs for SDNC.
VoLTE
SDNC team worked with equipment vendors of overlay network and jointly defined overlay TOSCA template. Underlay network development is on track.
Talked with Policy team to make sure all the development work to support VoLTE is on track.
A&AI team suggested VFC team to reuse existing node type instead of creating new one.
Developer Lab
Installed and tested ONAP1.1 last week and 6 VMs failed sanity test. Created JIRA tickets for all the blocking issues for sanity test. With the latest update, 4 VMs(DCAE, SDNC, APPC and MSO) are still failing sanity test
Worked with integration team to scrub JIRA high priority bug reports, and selected top blocking issues Amsterdam Integration Test Blocking Issues
E2E Integration Lab
The ONAP deployment environment is ready. Deployed WindRiver Titanium R4, the same with Developer lab.
ZTE and Huawei's tasks in TIC core are done
Huawei and ZTE, are deploying VNFs in TIC Edge to integrate with VIO 4.0, still in process.
Nokia is deploying vISCSCF, more virtual resources will be added to TIC core will extend more compute nodes.