OOM meeting notes - 2017-08-21
Meeting objectives:
How to we sync OOM with the integration lab? How do we enable the Integration team to do continuous integration work?
Considerations
OOM has focused yet on components defined here: OOM - M1 Release Planning Template. Most ECOMP component will be done in the next weeks
Updated list of "required" containers (realistic for R1) doesn't exist.
Concern is schedule
One thing to consider is to postpone OOM to R2.
Outcomes
Need to better define which containers should be part of R1. David to reach to each of the PTLs so that this list can be populated.
David to create a realistic view of OOM target for R1 so that PTLs can understand the firm decision.
David to make sure the "OOM how to" is documented so that each of the individual project teams can create their own OOM code (K8S config, Helm config). Ask PTLs if they can make it for R1.
Need to determine the easiest option for each of the PTLs.
David to organize OOM demo with each PTLs.
OOM to present at Integration meeting tomorrow, 10AM est