SO Weekly Meeting 9-19-2018
Update on so sprint 2 : No risk/ blocker reported
Workflow designer will be pushed in 2-3 days days
Pnp Workflow in testing, and to be finished in 2-3 days.
Defects
Highest and High priority issues to be handled on urgent basis to meet the M4 criteria
Rob would update on the below issues
SO-866 - Done
SO-1022 - Done
Security vulnerabilities - Will be shared by seshu
Bump the version - seshu
SO to be bumped to 1.3.1 after all the new features changes are merged.
So /libs are bumped to 1.3.0
Release Note to be updated for Casablanca - seshu
New Development branch criteria - Agreement within the community.
A new branch for the Dublin based development will be cut on 28th
Ask is to ensure to merge Critical/Major issue changes to both the master and Dublin dev branches after the cut.
Spring boot to be upgraded from 1.5.7 to 2.0 version in Dublin and work for that to be started in the separate branch.
Slots to be provided in the later meetings to discuss on the new features to be planned in Dublin and later releases.