PTL / Special TSC meeting 2020-10-12

PTL / Special TSC meeting 2020-10-12

We will start our meetings by mentioning the project's Antitrust Policy, which you can find linked from the LF and project websites. The policy is important where multiple companies, including potential industry competitors, are participating in meetings. Please review and if you have any questions, please contact your company legal counsel. Members of the LF may contact Andrew Updegrove at the firm Gesmer Updegrove LLP, which provides legal counsel to the LF.

Attendance 

Attended

Proxy (w/ @name)

Gov. Holiday

Did Not Attend

Attended

Proxy (w/ @name)

Gov. Holiday

Did Not Attend

Attendance is taken purely upon #info in Zoom Chat 

@Alla.Goldner

AMDOCS

 

@Jason Hunt

IBM

@Andreas Geißler

DT

 

@Lingli Deng

China Mobile

@Bin Yang

WindRiver

 

@Murat Turpçu 

Turk Telecom

@cl664y@att.com

AT&T

 

@Former user (Deleted)

Reliance Jio

@Ciaran Johnston (Ericsson)

Ericsson

 

@Olivier Phenix

Bell Canada

@Davide Cherubini

Vodafone

 

@Ranny Haiby

Samsung

@Dong Wang

China Telecom

 

@Seshu Kumar Mudiganti

Huawei

@Eric Debeau - proxy: @Morgan Richomme

Orange

 

@Srinivasa Addepalli

Intel

@Fernando Oliveira

Verizon

 

@Timo Perala (Nokia)

Nokia

Agenda

START RECORDING

Duration

Agenda Item

Requested by

Notes / Links

Duration

Agenda Item

Requested by

Notes / Links

1 hour

Cross-project discussions

@David McBride

@Kenny Paul (Deactivated)

October static license scan published Oct 5:  #144  

Calendar migration completed.

All calendar information is now in ONAP meetings:  https://lists.onap.org/g/onap-meetings

LF IT Support

 

 

Testing Environment

 

 

Testing Improvement

 

 

CSIT Review

@Lasse Kaihlavirta

@Morgan Richomme

Status on the CSIT tests

ToolChain Improvement

 

 

Documentation

 

 

Other Improvement suggestion

 

 

Subcommittee Updates for PTLs

 

 

Sharing Best Practices

 

 

IF TIME ALLOWS ....

15 mins

Release status

 

Guilin RC0 - TODAY

ACTION @Guangrong Fu to follow up with @Huabing Zhao MSB PTL regarding release status Oct 13, 2020
ACTION @David McBridefollow up with requirements owners and test leads to complete integration test status page

Status

Action Plan

  • Health check, Smoke test ==> 100%

    • Need to integrate SO for Guilin (currently using Frankfurt) 

  • SO - Seshu working with Sylvain

    • Deployment

    • TSC "must have" for SO

    • HTTP vs HTTPS (Java 11)

Honolulu

 

5 mins

Upcoming Events

 

Documentation Hackathon Days - October 14th, 2020

All PTLs, especially new PTLs, or PTLs that are introducing new documents, should attend at least one of these days.

TSC Meeting will be canceled on Oct 15th

LFN Fall Technical Meetings  October 13 - 15, 2020

  •  

    • Schedule

    • View the event wiki here and register here.

      • There is no cost to attend

      • TSC/Subcommittee Volunteers

        • @Ranny Haiby@Timo Perala (Nokia) , @Chaker Al-Hakim , @Seshu Kumar Mudiganti

10 mins

Remaining Action Items

 

 

Zoom Chat Log 

06:09:50 From Catherine Lefèvre (ONAP) : #info, Catherine Lefèvre
06:12:10 From Morgan Richomme - Orange : #info Morgan Richomme (proxy Eric Debeau)
06:16:52 From Catherine Lefèvre (ONAP) : @kenny, i have sent a note to the tsc
06:16:54 From Catherine Lefèvre (ONAP) : no worries
06:22:32 From Kenny PAUL (LFN) : https://lists.onap.org/g/onap-meetings
06:29:01 From Catherine Lefèvre (ONAP) : @kenny - will we use this page for RC0. or will we use the ptl page today- https://wiki.onap.org/pages/viewpage.action?pageId=84671848
06:29:17 From Catherine Lefèvre (ONAP) : if we use the PTL page then we need to add TSC attendance on the ptl page
06:32:49 From Catherine Lefèvre (ONAP) : @Kenny, I have sent a note to Bin yang, guangrong
06:49:51 From Morgan Richomme - Orange :  https://lf-onap.atlassian.net/wiki/display/DW/Moving+CSIT+to+project+repositories
06:50:04 From Catherine Lefèvre (ONAP) : Suggestion to also write to onap-release distro because all the PTLs are not attending today's call
07:01:15 From Kenny PAUL (LFN) : my dog is freaking out. sorry.
07:02:36 From Kenny PAUL (LFN) : i'm back
07:03:32 From Andreas GEISSLER (DT) : #info Andreas Geissler, DT
07:03:33 From Kenny PAUL (LFN) : #topic TSC Rollcall
07:03:39 From Timo Perala (Nokia) : #info Timo Perala, Nokia
07:03:44 From Bin Yang (Wind River) : #info Bin Yang, Wind River
07:04:04 From Dong Wang (China Telecom) : #info Dong Wang, China Telecom
07:04:38 From Fernando (Fred) Oliveira : #info Fred OLIVEIRA, Verion
07:04:39 From Jason Hunt (IBM) : #info Jason Hunt, IBM
07:04:40 From Srini Addepalli : #info Srini Addepalli, Intel
07:04:58 From Morgan Richomme - Orange : #info Morgan Richomme, Orange (Proxy Eric Debeau)
07:05:14 From Catherine Lefèvre (ONAP) : #info, catherine lefevre, att
07:05:38 From ALLAGO : #info Alla Goldner, Amdocs 
07:05:42 From ONAP Meeting 11 : #info Sunder Tattavarada (AT&T )
07:06:05 From ONAP Meeting 11 : sorry
07:10:27 From Catherine Lefèvre (ONAP) : 83% - great work since last night
07:11:26 From Catherine Lefèvre (ONAP) : thank you Guangrong ! let us know if any blocker from huanbing
07:11:53 From Guangrong FU (ZTE) : No problem.
07:14:22 From Olivier PHENIX (Bell Canada) : #info Olivier Phenix, Bell Canada
07:14:39 From Kenny PAUL (LFN) : @olivier thanks
07:48:33 From Catherine Lefèvre (ONAP) : https://lf-onap.atlassian.net/wiki/display/DW/2%3A+Frankfurt+Release+Integration+Testing+Status
07:50:34 From Kenny PAUL (LFN) : #ACTION @dmcbride contact test leads/owners to fill out the Guilin release integration status.
07:51:41 From Kenny PAUL (LFN) : ---
I must drop at the top of the hour to start another standing meeting.
07:55:59 From Kenny PAUL (LFN) : #info  Guilin RC0 is a no-go for today.  To be reviewed again next Monday.
07:58:13 From Kenny PAUL (LFN) : #ACTION @kenny set nect week's TSC infote for Guilin RC0 @ 13:00 UTC
08:00:15 From Kenny PAUL (LFN) : ^^invite
08:01:13 From Catherine Lefèvre (ONAP) : All the requirements owners to provide RC0 scorecard
08:01:31 From Catherine Lefèvre (ONAP) : Use case and functional reqs to provide their test plan as part of https://lf-onap.atlassian.net/wiki/display/DW/2%3A+Guilin+Release+Integration+Testing+Status
08:02:07 From Jessica Wagantall : sorry, need to drop for another meeting..

Action Items 