2020-08-19 Control Loop Sub Committee
Discussion items
Duration | Agenda Item | Requested by | Notes / Links |
---|---|---|---|
START RECORDING | |||
ATTENDEES
NOTES
Siva - team is going through the design, no updates.
Pam - update on Policy Guard Filter
Vijay - who is designated testers for Control Loop? Per Scott, Sebastien and Christophe will be fulfilling that role in Guilin.
TEST-251: Implement a basic clamp and basic closed loop testClosed - Integration team is doing some work.
New tcagen2 requires new blueprint and model for testing.
Committee created a new Integration Testing page to help track testing of Control Loops per release.
There are ONAP Virtual Tech meetings in mid-Oct - Control Loop has a slot for Honolulu discussion.