5G Use Case Meeting notes for Oct 17, 2019

5G Use Case Meeting notes for Oct 17, 2019

Date

Oct 10, 2019

Attendees

  • @Benjamin Cheung

  • @Swaminathan Seetharaman

  • @Borislav Glozman

  • @Dongho Kim

  • @Sandeep Shah

  • @Zu Qiang

  • @Oskar Malm

  • @Prabhu

  • @Bob Papa

  • 46107114668

  • @Milind Jalwadi (Unlicensed)

  • @Joanne Liu Rudel

Discussion items

Time

Item

Who

Notes

Time

Item

Who

Notes

 

M1 Deadline Deliverables

All in 5G U/C

M1 Deliverables, DEADLINE: Oct 31, 2019

TSC Evaluation & Integration leads - Deadline Oct 15, 2019

Release Planning Page: Release Planning

M1 Deliverables Checklist: Deliverables for Planning Milestone Checklist Template

(1) TESTING -  Integration Testing End-to-end use cases listed

(2) PTLs - commitments from the Platform component PTLs

(3) RELEASE PAGE - Frankfurt Release Requirements page needs to be updated.

(4) MODEL - Modeling Requirements Page for R6 (Planning)

ONAP R6 Modeling High Level Requirements

(5) CHECKLIST - Deliverables for planning milestone checklist template: Deliverables for Planning Milestone Checklist Template

Checking & cross-checking that Epic REQ-# Jira tickets are made (Sept 19)

 

INTEGRATION DISCUSSION Oct 17 2019 - Reviewed Release Requirements

ACTIONS:

  1. Harmonization U/C Identify Integration Lead

@Dongho Kim - discussing with Ericsson and AT&T who can commit. A1 adaptor unit testing.

For O1 part Nokia. CMnotif. fault, CallTrace(no), ...

@marge.hillis Need to find Integration Lead

2. RunTime Config DB Integration Lead

@Joanne Liu Rudelfind the Integration Lead

3. OOF/SON/PCI U/C Integration Lead

@Swaminathan Seetharamanto identify lead

4. Pre-onboarding/Onboarding U/C

  We do not need full E2E Integration @Zu Qiang , only need to integrate the new development in VNF-SDK

ACTIONS:

@Benjamin CheungContact @Catherine Lefèvrewhat does "Commit per company" mean in the RED Highlighted Commitment ... problem(?)
5G UseCase team needs to update the Commitment per Component per company on the Frankfurt Release Requirements release page

 

ORAN ONAP Plugfest Demos

All in 5G U/C

Realization Call Oct 16

Use Case Realization Call: October 16, 2019

Discussion with @Tracy Van Brakle

Demos will be on Dec 5, 2019 (AM EDT UTC-4 USA)

 

R6 Use Case Proposals / Requirements

All in 5G U/C

TSC Release Page.

Frankfurt Release Requirements

In the REQUIREMENTS Table of the R6 Release Requirements Wiki (above) the Use Case requirements as discussed on the TSC call for Sept 12, and @David McBride has asked that we have requirements (jiras) on separate rows. Further follow-up discussions will be had for "what is a use case" and if some of the 5G use cases should be moved up to the first table.

 

RunTime DB

 

@Joanne Liu Rudel

@Benjamin Cheung

Architecture S/C presentation for Run Time DB.

Documenting (1) Arch component wiki ARC RunTime DB Component Description - R6 Frankfurt

(2) Flow using Run Time DB. Presented Oct 15, 2019.

(3) Making RunTime DB as a separate common service component

   - Discussed at the Architecture S/C Oct 23.

(4) Need to present TSC AFTER approval from Architect S/C.

(5) Meeting with David McBride

 

Network Slicing R6 Proposal

@Borislav Glozman

@Shankaranarayanan Puzhavakath Narayanan

@Swaminathan Seetharaman

@LIN MENG

Update on slicing proposal. SO/Seshu presented.

Multiple functional requirements/Use Cases. Recursive orchestration of nested services. Didn't want independent W/F for flows but try to leverage/reuse work. Presented the End to End U/C with macro-view for E2E slice. and components impacted. Right now impact will be on SO, OOF, Policy, SDC and AAI. What controller will be used for managing slices? Focusing on design aspects and instantiation and activation. Put up logical E2E slice. Target simple VNFs. Focus to create VNF vs reconfiguring a VNF? Slice segments are going to be both dedicated/shared. Started with discovering existing resources; assume segments created with VNF/PNFs in inventory & discoverable. Spinup new slice instances.

Presentation/slides at: NETWORK SLICING PoC in R6 Frankfurt (Obsolete)

Convergence Plan Presented Oct 17, 2019

Setting up Regular meetings

 

Discussion: @Milind Jalwadi (Unlicensed)

JSON based screens for VID

would want to upstream that NSST NSSD

Part of the Network Slicing Use Case.

 

ORAN/3GPP ONAP Harmonization U/C

@Vimal Begwani

@marge.hillis

Trying to settle on scope of the Use Case. List of many possible contributions that will take more than one release to complete. Impacts for items to be added to wiki (analysis).

Prioritize the work items what we could propose to accomplish.

 

WoW w/ Model & Arch

 

Way of Working between Architecture , Modeling Subcommittee & Use Case Teams and what happens and touchpoints at M0/M1/M2/M3.

 

Use Case Template

5G U/C Team

Use Case Template - discuss updating the Use Case template & pages with some of these fields. Modeling team has said it would be useful for them to have the pre-condition & post-conditions, and information being passed (info-flows) documented.

Use Case Template

Filling out, describing and creating the Wiki for a Use Case

Use Case Tracking Template and Use Case Template

Proposed Functional Template for Use Cases

 

 

 

 

 

 

 

 

 

SUPPORTING SLIDES

Document

File

Document

File

Network Slicing Convergence Plan

@Swaminathan Seetharaman upload slides

Link to presentation (presented to ArchCom): E2E Network Slicing Joint Proposal

 

 

RECORDING

Recording

File

Recording

File

MP4 (Video + Audio)

Audio Only