Agenda:
Sync up the current coding status in each project
Issues clafication
Attendee:
LinMeng, BinYang, Fukuda, Ayumu, Masaaki, Satoshi, Razanne, Chuanyu Chen, Hongliang Bian.
Minutes:
Status Sync-up:
SDC: Coding already has been started. Front End and SDC Parser are on the rails, It has risks to finish the Back End before M4.
Ofir suggests to finish 70% unit test before M4 and it has risks to finish that. Lin will confirm the exact percentage of the completion of unit test before M4.
2. Mcloud:
DR function won't have much change in Mcloud. this release VMWare are focusing on the plug and play fulfillment .
ChinaTelecom has finished the ONAP environment in their lab. And will test SFC manually. They will do SFC automatic deployment in next release.
3. Vodafone side:
External API: Coding finished
SO-External API: In the process of Code review
Service decomposition: Still under analysis. In the process of drafting the service template that includes SPPartner
4. Service creation:
SO and UUI already starts the coding work. they need the parsing result of service template from SDC Parser. Lin will send Fujitsu an example and ask them to provide.