Status and Stucks
Current POMBA Casablanca Stories (Logging Project) -
Current Code Inspections
POMBA hourly healthcheck (CD deployment) - http://kibana.onap.info:5601/app/kibana#/dashboard/AWAtvpS63NTXK5mX2kuS
Note we are currently just barely meeting our line coverage rates with the addition of SDNC Context builder into Dublin, which impacts Casablanca since they are measuring main
Also CLM issues need to be addressed in SDNC Context Builder.
We have created all our Casablanca branches in POMBA project. Thanks James and Michael. SDNC ones have also been created.
Note sure about dependent A&AI release containers
General Status
Casablanca
Note that only committers can see nexus iq results so folks submitting code can't see what issues they are introducing. This is an issue for us.
Our code coverage currently lists us as passed.
Security related bugs being worked on:
LOG-830: Logging/POMBA CLM: fix/address/red-flag License org.json:json-20140107.jarClosed
LOG-831: Logging/POMBA CLM: fix/address/red-flag License javax.jms:jms-1.1.jar Closed
LOG-826: Logging/POMBA CLM: fix/address/red-flag jackson-databind-2.8.11.3 SECClosed
LOG-833: Logging/POMBA CLM: fix/address/red LA jackson-databind 2.5.1 SECClosed
Stability related issues being worked on:
Integration team still to close off a bug:
Dublin
SSL support necessary for AAI communications still in a holding pattern:
Note: Dublin OOM branch necessary to finalize bug fixes
They need to wait for the thumbs up from the integration team, so this may get impacted by the ONAP release delay
Still waiting on OOM branch for SDNC Context Builder deployment. (~November/December)
Technical Discussion
Chesla should provide an update on the TOSCA task force plan if there's anything new
No update
Integration Team discussion
Need schedule
How to test L2 Fabric
Some of that information may be not be available in ONAP
But the resources will be, even if for other reason.
Consider demo schedules
Making the PTL Happy
ONAP Casablanca RC2 Milestone
Logging Casablanca RC2 Deliverables for RC2 Milestone Checklist Template
Slipped to Nov 30th, but this just to allow more time for integration testing, not new work.
Anything new issues after the 15th does not need to be fixed
Dublin
CSIT needs to get done
Automated integration test that integration team can run. Need to get them.
Still open
Don't think we nee to present to architecture team this release as we are focused incremental improvements.
Consolidated monitoring
end to end monitoring - logging, kuberntets, etc
Improved logging.
Note we have not tested transaction ids in logs.
During operations.
They want single dashboard.