2019-01-31 (Jan 31)
Agenda
Status and Stucks
Technical Discussion
Making the PTL Happy
Notes
Status and Stucks
Current POMBA Dublin Stories (Logging Project) -
Current Code Inspections
POMBA hourly healthcheck (CD deployment) - http://kibana.onap.info:5601/app/kibana#/dashboard/AWAtvpS63NTXK5mX2kuS
General Status
Casablanca (Maintenance)
Nothing
Dublin
Tasks to be closed off (just a technicality):
Stories in progress:
SDNC-475: Netork Discovery - networkClosed: For network resource only and should be split into Network Discovery and ND context builder.
Stories to be formally verified before closure:
Bugs to enter:
Latest security scan results show ~9 medium issues that should be recorded (but aren't severe enough to merit immediate work).
Bugs entered in last week:
none
Bugs in progress:
LOG-803: POMBA: SDNC Context Builder passes lockedBoolean attribute with yes/no instead of the already established true/falseClosed (Verify in OOM fails, assigned back to design)
LOG-917: SDNCCtx Builder substitutes attribute names when not presentClosed (high)
Bugs to be verified:
Bugs closed off since last meeting:
Technical Discussion
Note OOM changes should be done when manifest changes are done. Should not wait for integration team to do this work for us.
We will have to do this for Dublin in two months.
Create task to track @J. Ram Balasubramanian
Done.
Docker version update
Moving from snapshot to proper release is part of workflow.
If POMBA thinks they will have no more changes, they can do this earlier
This is covered. We can stop tracking this here.
Organizing Models and Swaggers between releases
Basic navigation should take us to current
It should also be possible to get Casablanca information
Wiki needs some reorganization
Consider demo schedules
@J. Ram Balasubramanian will forecast demos as development progresses
Data Dictionary & Network Discovery- Dec 20
Done
L2 Network data - beginning of Feb?
Set a more specific date in January
Let's demo with some rules. So probably Feb 14th or 21st.
Additional enhancement - March 21st
Should ping the automation team on POMBA usage
Chesla to ping Brian.
Making the PTL Happy
Dublin
Should look at milestones and ensure we are in good shape.
Feature commitment Jan 17 → pushed one week. Jan 24th. (M1)
Prudence is supporting Michael for this activity.
https://lf-onap.atlassian.net/wiki/display/DW/Logging+Dublin+M1+Release+Planning
Functionality freeze Feb 14
Not sure if this was impacted by M1 slip.
API freeze is March 14th.