Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
Comment: add SDC sign-off


Table of Contents
outlinetrue

This page summarizes the projects that are within the scope of Beijing Release.

At M1 Release Planning milestone, Jan 18, 2018, the TSC will review all project planning materials and provide its disposition. It is expected that all projects intending to participate into Beijing submit their Project Planning Materials no later than Jan 8, 2018.

That will provide time for everyone to:

  1. understand each project scope
  2. review dependencies
  3. review all M1 materials
  4. ask openly question
  5. smooth the TSC approval process

Calendar for Beijing Release.

For those who intend to propose a new project, use the ONAP Project Proposal Template and post it in the Proposed Project list.

New project proposal for Beijing are available here. These new projects will be reviewed by TSC during Santa Clara F2F the week of Dec 11-13 amd added to the list below as they are approved byTSC.


M1 Status

Conditions on projects:

  1. AAF: Pass with condition TSC need to agree on expending to CSM sub project scope.
  2. AAI: Pass with condition TSC need to agree on expending to Image Manager sub project scope. Gildas Lanilis Gmail Update Feb 8. Team's decision to defer Image Manager to Casablanca.
  3. DCAE: Pass with condition on exception Cloudify manager.
  4. LOG: Pass with condition to review security guidelines and badges.
  5. OOM: Pass with Condition to Clarify Maturity scope.
  6. SO: Pass with Condition to reach 2 for Resiliency and Scalability at cpts Level (strectch ). Should be OK for 2 at Platform level.

Action Items:

  1. Benchmark-Integration (Jason-Helen) team to provide performance measurement by M2.Update by Gildas Lanilis Gmail: Information provided during Virtual F2F: Integration Testing and S3P Measurement (slide #17). Action Items: Closed
  2. Action Item: Auto-scaling: need for Blandford Scott and Zhao Peng to bring clarification on requirements. Update by Gildas Lanilis Gmail : Peng Zhao made clarification with VFC PTL, Scott Blandford broght clarification on the scope of Auto-scaling for Beijing. Action Items: Closed


M1 Summary of findings

PDF
nameONAP Beijing M1 Release PlanningV1.pdf

Link to M1 IRC notes.

M2 Status

TSC did not reach quorum today, therefore no vote took place. M2 Recommendations are provided and send out by email for vote.

Recommendations to TSC:

  1. Disposition M2 as Pass for aaf,aai, appc, ccsdk, clamp, cli, dcagen2, dmaap, doc, externalapi, holmes, integration, logging, modeling, msb, music, oof, oom, policy, portal, sdnc, so, vfc, vid, vnfrqts, vnfsdk. Update by Gildas Lanilis Gmail: TSC approved the disposition by mailing list vote.

  2. 3 projects (sdc, usecase UI, multicloud) could not make it today and are schedule for review at next TSC meeting. Update by Gildas Lanilis Gmail: TSC approved these 3 project during TSC meeting on Feb 22.
  3. TSC needs to discuss on VVP. Current status: VVP did not presnt to M1 and M2 and there are some thoughts on breaking thins into a sub-committe and a project.

Action Items:

  1. Auto-Scaling: carried over from M1. Peng Zhao and VFC team to clarify.See M1 note above. Action Items: Closed
  2. SO external API: Eric Debeau to contact Seshu Kumar Mudiganti for questions and concerns. Action Items: Closed

View file
nameONAP Beijing M2 Status Summary Version1.pdf
height250
View file
nameONAP Beijing Release V1.pdf
height250

Link to M2 IRC notes.

M3 Status

All projects except VVP and logging passed M3 milestone.

Action Items:

  1. Logging: checklist was not available. Review will be hold during next week TSC meeting. Action Items: Closed (datails here, slide #3)
  2. VVP: Steven wright to organize meeting to review and clarify S3P scope for VVP. (Invitees: Brian FreemanHelen ChenGildas Lanilis GmailAction Items: Closed (datails here, slide #4)

View file
nameONAP Beijing M2 Status Summary Version1.pdf
height250
View file
nameONAP Beijing Release V1.pdf
pageTSC 2018-03-08
height250

Link to M3 IRC notes.

M4 Status

All projects passed except: Usecase-ui, ExternalAPI, AAF, DMAAP. TSC was running out of time to provide its disposition on VVP.

Update on April 26: Usecase-ui, ExternalAPI, AAF, DMAAP passed M4.

Action Items:

  1. PTL: Look for details in colunm "M4 notes and Disposition" in PDF file, plus all the items highlighted in Red.
  2. PTL: ensure the Functional Requirement and Platform Maturity table are up to date
  3. PTL: update project risk

View file
nameONAP Beijing M4 Status Summary Version2.pdf
height250
View file
nameONAP Beijing Release M4 V1.pdf
height250

RC0 Status

All projects passed except: DCAE, Portal, ExternalAPI, AAF, OOF and LOGGING. Main focus is on OOM deployment. Details are provided in Excel Sheet Tab RC0 (filter on colunm M) or in PDF format.

Update on May 3: Portal, DCAE, Logging passed RC0

Note: Just after TSC meeting, I have been able to clear UseCaseUI-Server. There isn't anymore dependency on MySQL and build has no error.

View file
nameONAP Beijing RC0 Status Summary Version4.pdf
height250

RC1 Status

To pass RC1 criteria used were:

  1. Pass OOM and Heat Deployment
  2. Pass Pair Wise Testing

Between RC1 and RC2, Release manager will keep updating the table below.

PassConditional
CCSDK - May 3AAF
Doc - May 3DCAE
Integration - May 3External API
Modelling - May 3Logging
Music - May 3OOF
OOM - May 3AAI
Portal - May 3APPC
VNFRQTS - May 3CLAMP

CLI

DMAAP

HOLMES

MSB

MULTICLOUD

POLICY

SDNC

SO

VID

VFC

VNFSDK

VVP

USECASE UI

SDC

View file
nameONAP Beijing RC1 Status Summary Version1.pdf
pageTSC 2018-05-03
height250

View file
nameONAP Beijing Release RC1V3.pdf
pageTSC 2018-05-03
height250

RC2 Status

On May 17, TSC took decision to postpone RC2 and Sign-Off date by 2 weeks.

Beijing Release Planning has been updated accordingly.

New dates are:

  • RC2: May 31, 2018
  • Sign-Off: June 7, 2018

Materials presented on May 17 are:


Beijing Vulnerability Reports

This list projects who have fill out a vulnerability report for Beijing Release.

Filter by label (Content by label)
max30
cqllabel = "security"

Beijing Milestones Status


Project NameProject Tech. Lead

M0 Kick-Off/Intention Submission


M1

Planning

M2

Functionality freeze

M3

API Freeze

M4

Code Freeze

RC0

Release Candidate 0

RC1

Release Candidate 1

RC2

Release Candidate 2

Sign-Off

Release Delivery

1A & AI Oct 25, 2017

Planning

Checklist

Pass with condition

ChecklistChecklistChecklistChecklistChecklistChecklistChecklist
2Application Authorization FrameworkNov 5, 2017

Planning

Checklist

Pass with condition

ChecklistChecklistChecklistChecklistChecklistChecklistChecklist
3APPCNov 4, 2017

Planning

Checklist

Pass

ChecklistChecklistChecklistChecklistChecklistChecklistChecklist
4CLAMPOct 30, 2017

Planning

Checklist

Pass

ChecklistChecklistChecklistChecklistChecklistChecklistChecklist
5Common Controller SDKOct 13, 2017

Planning

Checklist

Pass

ChecklistChecklistChecklistChecklistChecklistChecklistChecklist
6DCAENov 4, 2017

Planning

Checklist

Pass with condition

ChecklistChecklistChecklistChecklistChecklistChecklistChecklist
7DMaaPNov 5, 2017

Planning

Checklist

Pass

ChecklistChecklistChecklistChecklistChecklistChecklistChecklist
8DocumentationNov 4, 2017

Planning

Checklist

Pass

ChecklistChecklistChecklistChecklistChecklistChecklistChecklist
9External API FrameworkNov 7, 2017

Planning

Checklist

Pass

ChecklistChecklistChecklistChecklistChecklistChecklistChecklist
10HolmesOct 26, 2017

Planning

Checklist

Pass

ChecklistChecklistChecklistChecklistChecklist

11

Integration

Oct 25, 2017

Planning

Checklist

Pass

ChecklistChecklistChecklistChecklistChecklistChecklistChecklist
12Logging Enhancements Project Oct 30, 2017

Planning

Checklist

Pass with condition

ChecklistChecklistChecklistChecklistChecklistChecklistChecklist
13Microservices BusOct 26, 2017

Planning

Checklist

Pass

ChecklistChecklistChecklistChecklist


14ModelingOct 26, 2017

Planning

Checklist

Pass

ChecklistChecklistChecklistChecklistChecklistChecklistChecklist
15Multi VIM/CloudOct 26, 2017

Planning

Checklist

Pass

ChecklistChecklistChecklistChecklistChecklistChecklistChecklist
16MUSICJan 4, 2018

Planning

Checklist

Pass

ChecklistChecklistChecklistChecklistChecklistChecklistChecklist
17ONAP CLIOct 26, 2017

Planning

Checklist

Pass

ChecklistChecklistChecklistChecklistChecklistChecklistChecklist
18ONAP Operations ManagerOct 26, 2017

Planning

Checklist

Pass with condition

ChecklistChecklistChecklistChecklistChecklistChecklistChecklist
19ONAP Optimization FrameworkNov 6, 2017

Planning

Checklist

Pass

ChecklistChecklistChecklistChecklistChecklistChecklistChecklist
20ONAP Usecase UI Project ProposalOct 26, 2017

Planning

Checklist

Pass

ChecklistChecklistChecklistChecklistChecklistChecklistChecklist
21Policy Framework Project ProposalOct 26, 2017

Planning

Checklist

Pass

ChecklistChecklistChecklistChecklistChecklistChecklistChecklist
22Portal Platform Project ProposalOct 26, 2017

Planning

Checklist

Pass

ChecklistChecklistChecklistChecklistChecklistChecklistChecklist
23SDN-COct 13, 2017

Planning

Checklist

Pass

ChecklistChecklistChecklistChecklistChecklistChecklistChecklist
24Service Design & CreationOct 28, 2017

Planning

Checklist

Pass

ChecklistChecklistChecklistChecklistChecklistChecklistChecklist
25Service OrchestratorOct 25, 2017

Planning

Checklist

Pass with condition

ChecklistChecklistChecklistChecklistChecklistChecklistChecklist
26VF-C: Virtual Function ControllerOct 26, 2017

Planning

Checklist

Pass

ChecklistChecklistChecklistChecklistChecklistChecklistChecklist
27VID projectOct 29, 2017

Planning

Checklist

Pass

ChecklistChecklistChecklistChecklistChecklistChecklistChecklist
28VNF SDKNov 20, 2017

Planning

Checklist

Pass

ChecklistChecklistChecklistChecklistChecklistChecklistChecklist
29VNF RequirementsNov 6, 2017

Planning

Checklist

Pass

ChecklistChecklistChecklistChecklistChecklistChecklistChecklist
30VNF Validation (VVP)Oct 31, 2017

Not reviewed by TSC.

Checklist created on March 1

Checklist created on March 1ChecklistChecklistChecklistChecklistChecklistChecklist