CLAMP R2 - M3 API Freeze Milestone Checklist

CLAMP R2 - M3 API Freeze Milestone Checklist

The following items are expected to be completed for the project to Pass the M3 API Freeze Milestone.

M3 Release Architecture Milestone overview is available in wiki.

Practice Area

Checkpoint

Yes/No

Evidences

Comment

Practice Area

Checkpoint

Yes/No

Evidences

Comment

Architecture



Has the Project team reviewed the APIs with the Architecture Committee (ARC)?

Yes

ONAPARC-113: CLAMPClosed



Review happened on 3/7/18

Is there a plan to address the findings the API review?

N/A

NA

No findings found during the review

Does the team clearly understand that no changes in the API definition is allowed without formal TSC review and approval?

Yes

NA

In the case some changes are necessary, bring the request to the TSC for review and approval.

Is there any changes in the scope, functionalities, deliverable, dependency, resources, API, repositories since M1 milestone?

No

NA.

All planned functionalities are still scheduled, at this time we are not aware of any change in plan/scope for clamp or its dependencies.

Provide link to the API Documentation.

Yes

http://onap.readthedocs.io/en/latest/submodules/clamp.git/docs/index.html

We don't expose api but uses api's from other project (policy, dcae and sdc). A story exists in Beijing to document CLAMP healthcheck API using SWAGGER, meanwhile API Documentation is provided in readthedocs.

Release Management

Are committed Sprint Backlog Stories been marked as "Done" in Jira board?

Yes

Backlog

Yes

Are all tasks associated with Sprint Backlog Stories been marked as "Done" in Jira?

Yes

Backlog

Yes

Have all findings from previous milestones been addressed?

Yes

No specific findings



Development

Has the project team reach the Automated Unit Test Code Coverage expectation? (Refer to artifacts available in Sonar)

Yes

Goal: 50% for Incubation project in Beijing

Link to Sonar results

CLAMP is now above the 50% target.

Is there any pending commit request older than 36 Business hours in Gerrit?

No





Do you have a plan to address by M4 the Critical  vulnerabilities in the third party libraries used within your project?

Yes

https://lf-onap.atlassian.net/browse/CLAMP-135

Currently only 5 Critical remains, an effort has already been done to remove most of them.

Are all the Jenkins jobs successfully passed ( Merge-Jobs)?

Yes

Jenkins project tab



Are all binaries available in Nexus?

Yes

link to Nexus project folder

SNAPSHOT Binaries at this stage.

Integration and Testing


Have 50 % of System Integration Testing Use Cases been implemented successfully in Jenkins?

Yes

Link to CLAMP CSIT

29 out of 41 tests have been reworked and passed.

Has the project code successfully passed the Daily Build process?

Yes

Jenkins project tab

Goal is to ensure the latest project commit has not broken the Integration Daily Build .