DMaaP R2 Beijing Release - M4 Code Freeze Milestone Checklist
The following items are expected to be completed for the project to Pass the M4 Code Freeze Milestone.
M4 Release Code Freeze Milestone overview is available in wiki.
Usage
Use the "Copy" option (available under the ..., top right of this page) to duplicate this template into your project wiki.
Fill out the Yes/No column
Provide link to evidence (when necessary)
Practice Area | Checkpoint | Yes/No | Evidences | How to? |
---|---|---|---|---|
Product Management | Have all JIRA Stories supporting the release use case been implemented? | Yes | Getting issues... | For each JIRA story that are implemented in Amsterdam Release, you have to setup in JIRA the JIRA fixVersion="Beijing Release" |
List the Stories that will not be implemented in this current Release. | No | For each JIRA story that will not be implemented in Amsterdam Release, you have to setup in JIRA the JIRA fixVersion="Beijing Release" | ||
Are committed Sprint Backlog Stories been coded and marked as "Done" in Jira? | Yes | Getting issues... | ||
Are all tasks associated with committed Sprint Backlog Stories been marked as "Done" in Jira? | Yes | Getting issues... | ||
Release Management | Have all issues pertaining to FOSS been addressed? | Yes | ||
Have all findings from previous milestones been addressed? | N/A | List previous milestone issues that have not been addressed. | For M2 and M3 Milestones, ensure all findings have been closed. | |
Has the Project Team reviewed and understood the most recent license scan reports from the LF, for both (a) licenses within the codebase and (b) licenses for third-party build time dependencies? | Yes | |||
For both (a) and (b), have all high priority non-Project Licenses been either removed or escalated as likely exception requests? | Yes | Created a ticket#54030 to address the issues in DMaaP client project. | ||
Development | Are all Defects of priority Highest and High in status "Done" in Jira? | Yes | Getting issues... | |
Has the project team reach the Automated Unit Test Code Coverage expectation? (Refer to artifacts available in Sonar) | No | https://sonar.onap.org/projects?search=dmaap&sort=-analysis_date Note: - All Message router projects has 50% code coverage. - In Bus Contorller, dmaap-dbcapi and dmaap-buscontroller has met 50% code coverage. ui-dmaapbc not met the code coverage. | For evidences, provide link(s) to Gerrit repos by providing the URL as shown in this example | |
Is there any binaries (jar, war, tar, gz, gzip, zip files) in Gerrit project repository? | No | |||
Is there any pending commit request older than 36 hours in Gerrit? | No | |||
Provide the "% Achived" on the CII Best Practices program. | 97% | https://bestpractices.coreinfrastructure.org/en/projects?q=messagerouter | As documented in CII Badging Program, teams have to fill out CII Best Practices | |
Is there any Critical level security vulnerabilities older than 60 days old in the third party libraries used within your project unaddressed? Nexus-IQ classifies level as the following:
which is complaint with CVSS V2.0 rating. | No | Some of the security vulnerabilities reported in the following checklist are less then 60 days old and some are wrongly reported. | Ensure the Nexus-IQ report from “Jenkins CLM” shows 0 critical security vulnerability. Open the Nexus-IQ report for the details on each repo. | |
Are all the Jenkins jobs successfully passed (verify + merge jobs)? | Yes | |||
Are all snapshot binaries available in Nexus? | Yes | |||
Do you have a clear plan to implement the Independent Versioning and Release Process by RC0? | Yes | Contact the upstream teams to make sure they will release their artifacts (in Nexus Release repo) so you can build by depending on these released artifacts by RC0. | ||
Integration and Testing | Have 100% of Continuous System Integration Testing (CSIT) Use Cases been implemented successfully in Jenkins? | No | Message Router - 100%complete https://jenkins.onap.org/view/CSIT/job/dmaap-master-csit-mrpubsub/ Bus controller - In progress | |
Is there a Docker images available for your project deliverable? | Yes | |||
Has the project code successfully passed the Daily Build process? | Yes | Goal is to ensure the latest project commit has not broken the Integration Daily Build | ||
Doc | Has the team created a docs folder and Development and Release Notes documentation templates in Readthedocs? | Yes | . | Documentation Team is using Readthedocs for documenting user facing documentation. ReadTheDcos shall be considered as a starting point for someone new within ONAP. The ReadTheDocs is the ONAP Documentation facade visible to users. |
Is the API documentation section populated? | No | Message router: http://onap.readthedocs.io/en/latest/submodules/dmaap/messagerouter/messageservice.git/docs/index.html Bus Controller : In progress | Ensure there is at least a direct link toward the API documentation which may be already existing in the wiki. |