Amsterdam Release Planning: M1 Project Review
7 minutes to review each project and TSC take project disposition.
Review Friday, June 30
Project | PTL | Release Planning Artifacts | Release Planning Checklist | Time UTC | TSC Disposition | |
---|---|---|---|---|---|---|
1 | Virtual Function Controller | Yan Yang | 14:05 | Review approved w/ contingencies- 1) trim down the committer list. 2) arch subcommittee decision on SO next week. | ||
2 | Holmes | Guangrong Fu | 14:12 | Review approved w/ contingency PTL for holmes, dcae, clamp & policy provide recommendation to TSC next week . | ||
3 | CLAMP | Gervais-Martial Ngueko | 14:19 | Review approved | ||
4 | Microservices Bus | Huabing Zhao | 14:26 | Review approved w/ contingency - trim down the committer list | ||
5 | CLI | Kanagaraj Manickam | 14:33 | -- not reviewed -- | ||
6 | Usecase UI | Shen Tao | 14:40 | Review approved w/ contingency - complete the checklist | ||
7 | Software Defined Network Controller | Dan Timoney | 14:47 | Review approved w/ contingency- discussions over VoLTE usecase requirements with SDN-C | ||
8 | Policy Framework | Pamela Dragosh | 14:54 | Review approved | ||
9 | Portal Framework | Leimeng Shi (backing ip Manoop Talasila) | 15:01 | Review approved w/ contingencies- 1) upload image file to the wiki -assistance needed 2) solicit additional community participation | ||
10 | VNF-SDK | Christopher Donley | 15:08 | Review approved | ||
11 | Data Collection, Analytics, and Events | Vijay V Kumar (backing up Lusheng Ji) | 15:15 | Review approved w/ contingencies- 1) move VESCollector from incoming to outgoing API dependencies 2) clean-up contributor list- too many blanks | ||
12 | VNF Validation Program | Erik Sundelof | 15:22 | Review approved | ||
13 | Active and Available Inventory | Jimmy Forsyth | 15:29 | Review approved | ||
14 | Application Controller | Randa Maher | 15:36 | Review approved w/ contingencies- 1) in/out API section needs to be updated based upon information previously discussed in this session - review next Friday 2) checklist to be completed | ||
15 | Modeling | Hui Deng | 15:43 | -- not reviewed -- | ||
16 | 15:50 |
Review Friday, July 7
Project | PTL | Release Planning Artifacts | Release Planning Checklist | Time UTC | TSC Disposition | |
---|---|---|---|---|---|---|
1 | Modeling | Hui Deng | 14:05 | Review approved w/ contingency resource allocation updates | ||
2 | Service Orchestrator | Seshu Kumar | 14:12 | Review approved w/ contingency resource allocation updates | ||
3 | Multi VIM/Cloud | Xinhui Li | 14:19 | Review approved w/ contingency on resource allocation and action of risk section | ||
4 | VNF Requirements | Steven Wright | 14:26 | -- not reviewed -- | ||
5 | CLI | Kanagaraj Manickam | 14:33 | Review Approved | ||
6 | Integration | Helen Chen | 14:40 | Review Approved | ||
7 | CCSDK | Dan Timoney | 14:47 | Review Approved | ||
8 | DMAAP | Ram Koya | 14:54 | -- not reviewed – move to tsc meeting | ||
9 | Documentation | Rich Bennett | 15:01 | Review Approved | ||
10 | External API Framework | Andy Mayer | 15:08 | Review approved | ||
11 | ONAP Operation Manager | David Sauvageau | 15:15 | Review Approved w/ contingency on resource allocation and checklist | ||
12 | Optimization Framework | Sarat Puthenpura | Project planned for Beijing Release. No need to be reviewed. | 15:22 | -- Beijing release, not Amsterdam -- | |
13 | Review of June 30, action items | 15:29 | ||||
14 | Network Function Change Management project proposal | Emmanouil Mavrogiorgis | 15:45 | Will be handled either as a subcommittee otr a use case for the Beijing release. Proposal is withdrawn. |
Review Thursday, July 13
Project | PTL | Release Planning Artifacts | Release Planning Checklist | Time UTC | TSC Disposition | |
---|---|---|---|---|---|---|
1 | Virtual Infrastructure Deployment | Amichai Hemli | 14:05 | Project artifacts not complete. Required work. Catherine will lead the effort. Next review scheduled in July 20. Project reviewed and approved by TSC on July 20. | ||
2 | Service Design & Creation | Eden Rozin (backing up Michael Lando) | 14:12 | Approved with following to work on:
| ||
3 | Logging Enhancements | Luke Parker (backing up Mark Pond) | 14:19 | Approved
| ||
4 | Application Authorization Framework | Ram Koya | 14:26 | Approved
| ||
5 | DMAAP | Ram Koya | 14:33 | Approved with following to work on:
| ||
6 | VNF Requirements | Steven Wright | 14:40 | Approved with following to work on:
| ||
7 | University | Nermin Mohamed | Decision to update the community after meeting with LF on July 14. | 14:47 |