12-13-2017 Portal Platform Weekly Meeting

Agenda:

  1. Review status on items assigned last week

  2. Go over JIRA list assigned for Beijing release

  3. Discuss M1 planning and check list for Beijing release

Attendees:

@Chris Lott, Lorraine Welch, @Weiting@Leimeng Shi@Sunder Tattavarada, MULLICK, GARIMA, Farhan Mir

Discussion Items:

  1. Extend Portal-119 to split DB for Portal and SDK - Chris

  2. Sent grep scan on "master_dev" branch to check if "ecomp" appears in Portal - Lorraine

  3. SDK will be next to scan - Lorraine

  4. Sent email to partners about SDK 1.3.2 - Leimeng

  5. Split Portal-19 to Jima and Robert (based on Lorraine's scan output)

  6. JUnit /Sonar coverage to 50%, assigned to Hima

  7. Discussed remaining JIRA items in great details

  8. Beijing Release Planning:

  9.  

    1. M0 - dev kick-off, Nov 16

    2. M1 - planning Jan 16

    3. M2 -  functionality freeze Feb 15

    4. M3 - API freeze Mar 1

    5. M4 - code freeze Apr 5