Release Planning: Guilin

Release Schedule r4 

 

 

Change Log

Date

Event or Update

Milestones Affected

Date

Event or Update

Milestones Affected

June 24

Initial version of schedule approved by TSC by mail vote.

N/A

July 9

M1 milestone requirements not met.  TSC agrees to slip M1 to July 13.

M1

July 13

M1 milestone requirements not met.  M1 slips to July 16.

M1

July 16

Project milestone status 100%, but requirements still not resolved. M1 slips to July 23.

M1

July 23

TSC approved M1 (2 week slip from original plan)

M1

August 6

M2/3 milestone reqirements not met.  M2/3 slips to August 11

M2/3

August 13

TSC approved M2/3 with conditions

M2/3

September 10

TSC agrees that M4 milestone requirements not met.  Agrees to review again on Sept 17.

M4

September 17

TSC approves M4 with exceptions

M4

September 18

Propose moving RC0 to Oct 12, and remaining milestones move out by 1 week (sign off, Nov 12).

RC0, RC1, RC2, Sign-off

September 24

TSC approved moving RC0 to Oct 12, and remaining milestones out by 1 week

RC0, RC1, RC2, Sign-off

October 12

RC0 requirements not met

RC0

October 19

RC0 requirements not met

RC0

October 22

Proposal:
Move RC1 to Nov 5
Move RC2 to Nov 19 and combine with Sign-Off

RC1, RC2, Sign-Off

October 22

RC0 approved with caveat that war room continue to resolve SO/OOM issues

RC0

October 22

Schedule proposal approved

RC1, RC2, Sign-Off

November 12

TSC approved merging RC1 with RC2 and sign-off on Nov 19

RC1, RC2, Sign-Off

November 19

RC1 / RC2 / Sign Off moved to Dec 3

RC1, RC2, Sign-Off