Release Planning: Honolulu

Release Schedule r5 (approved Apr 15, 2021 )

Activity Log

Date

Event or Update

Milestones Affected

Date

Event or Update

Milestones Affected

Apr 29

TSC approved Honolulu sign-off

Sign-Off

Apr 15

TSC approved schedule (r5)

RC1, RC2, Sign Off

Apr 8

Proposal for RC1, RC2, Sign Off (r5) (Note: r4 proposed but not approved)

RC1, RC2, Sign Off

Apr 2

Proposal for RC1, RC2, Sign Off (r4)

RC1, RC2, Sign Off

Apr 1

Consensus with OOM and INT that RC0 requirements met (TSC e-mail vote in progress). Action to propose schedule for RC1, RC2, Sign Off

RC0

Mar 29

RC0/RC1 requirements not met.  Re-evaluate on April 1.

RC0, RC1

Mar 25

RC0/RC1 requirements not met.  Re-evaluate on Mar 29.

RC0, RC1

Mar 18

TSC approved plan to merge RC0 with RC1 on March 25

RC0

Mar 11

TSC approved schedule proposal (see Mar 10 below)

RC0, RC1, RC2, Sign Off

Mar 10

Blocking issue reported for RC0. Propose 1 w slip to RC0 → Sign Off (r2).  Sign off moves to April 8.

RC0, RC1, RC2, Sign Off

Mar 1

TSC approves M3 with exceptions.  Exceptions to be closed by RC0.

M3

Feb 25

TSC determined that there is insufficient information to make decision, so M3 pushed out 4 days to March 1

M3

Feb 1

Uploaded ONAP Honolulu r1 to show changes to M1 and M2 dates

M1, M2

Jan 25

M2 approved with exceptions

M2

Jan 21

Requirements not met. M2 slipped to Jan 25

M2

Jan 14

M1 approved with exceptions

M1

Jan 11

Requirements not met.  M1 slipped to Jan 14

M1

Dec 10

TSC approved schedule

ALL

Dec 10

M1 moved out 4 days to Jan 11

M1

Nov 20

Second draft posted

 

Nov 11

First draft posted