Release Planning: Istanbul

Release Schedule 

Approved by the TSC on October 21, 2021 (r6)

 

Activity Log

Date

Event or Update

Milestones Affected

Date

Event or Update

Milestones Affected

Nov 15

Recommended sign off to the TSC.  Email vote launched.

Sign Off

Nov 4

The TSC delayed Sign Off to Nov 15.  https://lf-onap.atlassian.net/wiki/x/KDrs

Sign Off

Oct 21

The TSC approved RC under the condition that the remaining tasks will be completed by Sign Off.  The TSC also approved moving the Sign Off date out one week to Nov 4 (r6).

RC, Sign Off

Oct 18

The TSC agreed that the requirements for RC were not reached.  Will review again during the TSC meeting on Oct 21.

RC

Oct 14

The TSC agreed that the requirements for RC were not reached.  Will review again during the PTL meeting on Oct 18, followed by an email vote.

RC

Sept 16

TSC approved M4 with conditions.

M4

Sept 9

Remaining M3 items closed 

M3

Sept 2

TSC approved M3, conditioned on completion of remaining milestone tasks by M4

M3

Aug 26

TSC approved one week slip to M3.  No other milestones affected (r5).

M3

Jun 23

M2 approved by TSC, with exceptions, by email vote.

M2

May 20

M1 approved by TSC, with exceptions.  Details here.

M1

May 10

Added ONESummit dates to the schedule (r4) for reference.  (No changes to Istanbul release milestones from r3)

None

May 6

Approved by the TSC (r3)

ALL

May 4

New proposal (r3) in response to feedback at May 3 PTL meeting

  • Collapsed 3 RCs into a single RC

  • Added more time from M4 to RC

  • Added an additional week between RC and sign off

  • Corrected dates for China National Day holiday. Should be 10/1 -8, instead of 9/27 - 10/1.

RC0, RC1, RC2

Apr 28

New proposal (r2) in response to feedback from original proposal.

M1 - Sign Off

Mar 18

Proposal presentation to TSC.  Requested approval of just the kickoff date of April 1.  Other milestones to be discussed at a later date.  TSC approved kickoff date ONLY.

M0

Mar 11

Proposal presentation to TSC. TSC expressed concerns about the second half of the release occurring during the summer, which could conflict with summer holidays.  Proposal not approved.

ALL

Mar 10

Second draft

  • Added a new milestone  before M3

  • Previous "M3" becomes M4

  • Added event in June

  • Moved Honolulu sign off to April 8

Mar 4

Initial draft posted

N/A