Release Planning (legacy)
El-Alto Release
El-Alto Release Planning
The El-Alto release content is being planned. Currently the proposed contents include:
Refactoring
JIRA Backlog Reduction (defects, etc.)
Vulnerability issues
Test Coverage including jS
Test Automation & CI/CD pipeline
Deployment procedure
Documentation
The release contents will be prioritized at the 2019 El-Alto DDF in Stockholm.
TSC priorities:
Security
Documentation
Don't break the build
El-Alto Release Calendar
El-Alto Release Calendar (tabular)
Milestone | Date | Deliverable | Notes |
---|---|---|---|
Dev1 Start | Jul 15, 2019 | Vetted Jira list for the EarlyDrop (ED) | List of planned jiras for the development sprint (M1) |
M1 checkpoint | Jul 18, 2019 | TSC reviews and sign-off on intended El Alto Content | Content defined by fixVersion = "El Alto Release" Early Drop content defined by: label contains "El_Alto_Early_Drop" |
Test Plan Review | Jul 25, 2019 | Early drop and Final release test plan review and sign off by TSC |
|
Test1 Start | Jul 29, 2019 | Test to deliver ED | Phased integration and test plan. (M4_early_drop) Run daily sanity on El Alto released images, and start vFW, vLB and vCPE use case testing All containers for ED are due to be delivered to testing/integration |
Dev1 End | Aug 2, 2019 | Priority 0 vulnerabilities addressed | List of completed jiras due API documentation complete Arch changes reviewed and documented |
Dev2 Start | Aug 5, 2019 | Fixes only to support ED | Integration team drives bug list priority. All other development deferred check in until Dev3 Integration will work with dev teams to close highest/high priority jiras discovered during integration test. All integration tests should be finished three days before ED release so we will have time to update release note, put tag on branches, etc. |
Dev2 End | Aug 16, 2019 | ED released | Complete release - includes rel_notes, named release, branch. (M2/M3 milestone) |
Test1 End | Aug 16, 2019 | ED released | Complete release - includes rel_notes, named release, branch. (Sign_off_early_drop) |
EarlyDrop | Aug 21, 2019 |
|
|
Dev3 Start | Aug 19, 2019 |
|
|
Test2 Start | Aug 19, 2019 |
|
|
Dev3 End | Sep 6, 2019 |
| All code complete (M4)
|
Test2 End | Sep 6, 2019 |
|
|
Test3 Start | Sep 9, 2019 |
| Pair-wise testing (1 wk only) and Integration (RC0 - 9/19) All containers due to be delivered to testing/integration |
Test3 End | Oct 3, 2019 |
| All docs complete: reviewed and cherry-picked into stable |
El Alto Release | Oct 10, 2019 |
|
|