This page summarizes the projects participating into Casablanca Release.
...
Deck as approved on July 5 is available in wiki.
View file | ||||||||
---|---|---|---|---|---|---|---|---|
|
July 19 Update: Scope Change. From a Casablanca scope perspective, there are 2 additional functional requirements added:
- Change Management – Trafic Migration
- Change Management – PNF Software Upgrade
Slide deck has been updated accordingly. View file name ONAP Casablanca M1 Status Summary Version5.pdf height 250
M2 Status
All projects passed M2 Functionality Freeze. TSC Approval (Topic #5, Section Y )
View file name ONAP Casablanca M2 Status Summary Version1.pdf page TSC 2018-07-26 space Meetings height 250
View file name ONAP Casablanca Release Checklist V2.pdf page TSC 2018-07-26 space Meetings height 250
M3 Status
M3 review took place on August 23, 2018.
...
View file | ||||||||
---|---|---|---|---|---|---|---|---|
|
View file | ||||||||
---|---|---|---|---|---|---|---|---|
|
M4 Status
M4 review took place on Sept 20, 2018.
...
View file | ||||||||
---|---|---|---|---|---|---|---|---|
|
View file | ||||||||
---|---|---|---|---|---|---|---|---|
|
M4 Outcome
TSC approved the Release Manager Recommendations. Link to approval.
...
-  Slide #4: Michael Lando to review Bugs impacting HPAÂ
1 SDC defect fixed, one still in WIP. ETA: planned for beg next week.Status colour Green title Done -  Slide 7-12: Vimal Begwani to provide status on 5 G implementation STATUSÂ
ÂStatus colour Yellow title WIP
      5G Plug & Play: Brian Freeman Follow up on PRH HealthCheck within DCAEÂStatus colour Green title Done
      5G/PNF: Lifecycle Managament Support: Tracy Van Brakle and Jorge Hernandez to confirm that the necessary Ansible playbooks were delivered,
      and the necessary directed graph updates were made to invoke those playbooks
      5G: Bulk PM: Vimal Begwani File collector WIP. ETA Oct 4.ÂStatus colour Green title Done -  Slide 12: Sarat Puthenpura to provide ETA on 5G Performance Analysis and Optimization STATUSÂ
Status colour Green title Done - Â Slide #16: PTLs to update Casablanca Platform Maturity table at https://wikilf-onap.onapatlassian.orgnet/wiki/display/DW/Casablanca+Release+Platform+Maturity.Â
  Modeling (Hui Deng), VID (Ofir Sonsino)Status colour Red title Missing -  Slide #16: Gildas to add Platform Maturity table in M4 checklist. STATUSÂ
Status colour Green title Done - Â Slide #23:Â cl664y@att.com to update status on OSAM/PNF (postpone to Dublin or not) STATUS:
OSAM postpone to Dublin.Status colour Yellow title Postponed -  Slide #25: Impacted PTLs to fix CSIT Failure. STATUSÂ
 for DCAE, Multicloud, VFC, ExtAPI, DMAAP,OOF.Status colour Green title Done -  Slide #27: Jonathan Gathman and Michael Lando to increase code coverage for aaf-auth and sdc master and provide update on repos for which there is no report in Sonar.Â
...
-  Slide #28: Impacted PTLs to publish Vulnerability report. Steven Wright to follow up with Gildas Lanilis Gmail for VVP. STATUSÂ
 for VVP, Multicloud, Modeling, MUSICÂStatus colour Green title Done
         Â
  UseCase UI (Tao Shen)Status colour Red title Missing -  Slide #29-30: Impacted PTLs: Clean or Fix Job Failure
        Â
 Logging(Michael O'Brien)ÂStatus colour Red title FAILURE
 for APPC,HOLMES, AAI, AAF ÂStatus colour Green title Done -  Slide #32: OOF team to ensure Healthcheck passes. STATUS Â
OOF pass on both Wind River OOM Release and Staging.Status colour Green title Done - Â Slide # 33 Risks: Jonathan Gathman and Manoop Talasila to address risks #3 on CADI. STATUS: Risk #3 closed.Â
Status colour Green title Done
...
View file | ||||||||
---|---|---|---|---|---|---|---|---|
|
RCO Outcome:
Projects Passing RC0:
...
Conditional on all other Projects in addressing Orange and Red Items (in above slides) related to:
- Pair Wise Testing: MUST be completed by RC1
- HealthCheck, focus on OOM environment, to be addressed by Oct 15
- Docker artifacts: to be delivered by Friday, Oct 12 COBbe completed by RC1
- HealthCheck, focus on OOM environment, to be addressed by Oct 15
- Docker artifacts: to be delivered by Friday, Oct 12 COB.
RC1 Status
RC1 review took place on Oct 25, 2018.
Materials:
View file | ||||||||
---|---|---|---|---|---|---|---|---|
|
RC1 Outcome:
Projects Passing RC1:
AAI
AAF
Clamp
Cli
Dmaap
Doc
ExtAPI
Integration
Pomba (sub project)
MSB
OOM
SO
VFC
VNFRQTS
VNFSDK
VVP
Update on RC1 on Nov 6:
Based on progress made since RC1 on Oct 25, and presented at PTL meeting on Nov 5, the following projects qualifies for passing RC1:
- APPC
- CCSDK
- DCAE
- Log
- Multivim
- Music
- Portal
- SDC
- Usecase UI
RC2 Status
By TSC decision on Nov 8, RC2 Milestone has been pushed to Tuesday, Nov 27 and Release Sign-Off to Friday, Nov 30.
Casablanca Milestones Status
____________