SO Casablanca - RC1 Milestone Deliverable Checklist

DRAFT PROPOSAL FOR COMMENTS

The following items are expected to be completed for the project to Pass the Release Candidate Milestone.

This template must be filled out for every Release Candidate Milestone (RC0, 1, 2, x)

RC Release Candidate Milestone overview is available in wiki.



Usage

  1. Use the "Copy" and "Move" options (available under the ..., top right of this page) to duplicate this template into your project wiki.

  2. Fill out the Yes/No column

  3. Provide link to evidence (when necessary)

Practice Area

Checkpoint

Yes/No

Evidences

How to?

Practice Area

Checkpoint

Yes/No

Evidences

How to?

Product Management

Are all tasks associated with the release been marked as "Closed" in Jira?

Yes







Have all findings from previous milestones been addressed?



Dynamic cloud owner SO-1128

SO <->SDNC interface over the cloud configuration





Development

Have all Defects of priority Highest and High been in status "Closed" in Jira?







Are all JIRA issues used as a reference in a commit in status "Closed" in Jira?

Yes



Very often, some JIRA issue remains in status "Todo" in JIRA while the commit they are referenced to is successful.

Is there any pending commit related to Highest and High priority issues older than 36 hours in Gerrit? In case there are messages going back and forth between authors and reviewers, it is acceptable to be above 36 hours.

No





Are all the Jenkins jobs successfully passed (verify + merge jobs)?

Yes

https://jenkins.onap.org/view/so/



Has the team delivered all their release artifacts in Nexus Release repo?

There should be at least ONE version of each artifacts available in Nexus Release repo.

Yes

https://nexus.onap.org/content/repositories/staging/org/onap/so/

https://nexus.onap.org/content/repositories/releases/org/onap/so/

Refer to Independent Versioning and Release Process for procedure

Integration and Testing

Have all CSIT Use Cases (created by each project team) passed?

Yes

https://jenkins.onap.org/view/CSIT/



At RC0, has the Pair Wise testing table been filled out?

WIP

Casablanca Pair Wise Testing master page





At RC0, have all OOM Release Healtcheck related to your project passed?

Yes





At RC0, is there a Docker image in Nexus Docker-Release repo available for each repository?

Yes

https://nexus3.onap.org/#browse/browse:docker.snapshot



Has the project code successfully passed the Daily Build process?

Yes



Goal is to ensure the latest project commit has not broken the Integration Daily Build 

Has the OOM deployment passed?

Yes

Ensure in Jenkins External Labs all Health Check pass. since 24th



Has the Heat deployment passed?

(not a gating item for Casablanca)

NA

Ensure in Jenkins External Labs all Health Check pass.



Documentation

For RC0, for project delivering binaries, has the team populated and validated all the sections of either the Platform Component or SDK template?



Yes

See https://onap.readthedocs.io/en/latest/submodules/vnfsdk/model.git/docs/index.html



Note that VNFSDK fits neither the Platform nor the SDK templates. We have filled out the relevant sections.

Most teams have already created the high level file structures in readthedocs, and populated some actual documentation. However, the remaining sections of the appropriate template must be completed.

Platform: A&AI, APP-C, CLAMP, CLI, DCAE, DMaaP, Holmes, MSB, OOM, Policy, Portal, SDN-C SDC, SO, UseCase UI, VFC, VID

SDKs: AAF, CCSDK, External API Framework, Multi VIM/Cloud, VNFSDK

For RC1, has the team addressed any issue (recorded in JIRA) provided by the Documentation team?

N/A

No JIRA tickets from Documentation team





For RC2, for project delivering binaries, has the team populated and validated all the sections of the Release Notes template?

NA





For RC2, has the Documentation Team provided the final approval for your project documentation?

NA