02-21-2018 Portal Platform Weekly Meeting
Agenda:
Check readiness of new CSIT team (Sireesh) on Robot test plan - Portal R2 Beijing Functional Test Cases
Portal JUnit code coverage 50% target (Hari team)
Review status on items assigned to dev team
Go over JIRA list assigned for Beijing release
Attendees:
Sireesh, Hari, Girish, Naveen, Raghavendra, Ritesh, Snigdha, Surajit, @Weiting, @Leimeng Shi, @Sunder Tattavarada, BINDU ELISETTY, HIMA (hbindu@research.att.com),
Farhan Mir, @Manoop Talasila
Discussion Items:
Sireesh started setting up local environment for robot test and reviewing test cases from previous release.
will contact Leimeng to know new features;
Hima will help setup the Portal in local testers machine.
vm11 test environment to check the bugs and to perform testing - Sunder/Leimeng discovered issue where new function code introduced, but not in DML script.
AAF integration with SDC - help Micheal Lando - Sunder/Leimeng Leimeng will send document to partners (check with Sunder too)
Portal-182 - CLI integration help - Leimeng to setup a working session - @Sunder Tattavarada/@Former user (Deleted)
Start working on Jan 31st – Leimeng will organize a call with Sunder/CLI team on Wed 9:00am (Sunder could not join the meeting, when is the next meeting?)
Portal-155 - security issues scan - Nexus IQ and Coverity scans
Need Access on Nexus IQ - Farhan/S
Coverity scan followup with Stephen.terrill@ericsson.com - Farhan
many user stories created regarding this big item, pending to assign to developer. (assigned to Sudeep)
Security issues status from CLM - Sudeep
Plan to release SDK 2.1.0 version and then communicate to partners to update their poms - Sunder/Leimeng - ETA 1/19. ==> update ETA to 1/25 - Sunder need help to find
Sunder emailed to LF team - however, LF team asked for latest build reference as the last build is 2 weeks old.
Extend Portal-119 to split DB for Portal and SDK - Robert - design session pending and ETA on dev tasks.
Robert is using VM3 for this effort. → 70% done by Robert
Update the deployment scripts with docker image name changes -
demo repo (heat templates);
integration repo (CSIT test deployment scripts);
OOM deployment;
Sent grep scan on "master_dev" branch to check if "ecomp" appears in Portal - done - Hima will be cleaning up - ETA 1/10.
ECOMP keyword in license text - followup with Catherine - Manoop ETA 2/16 ==> still pending
java class names - we can leave it as is
JUnit /Sonar coverage to 50% on SDK and Portal.
SDK - JUnit test coverage reached 14% - Hima (pending code review and push to gerrit) - Code need to push to gerrit - PORTAL-161: Add the JUNIT plumbing for PortalSDKClosed
Shireesh will coordinate his team with Hima and Kishore Gujja
Portal - target 30% to 50% - Girish/Hari team will continue from Gerrit -PORTAL-136: Raise JUnit test coverage ONAP Portal to 50% for BeijingClosed
Hari is coordinating the remaining code coverage on Portal (right now it is at 44%)
Manoop to followup with Gildas on the Sonar upgrade issue which got 2% down for portal form 40 - 38% (this is due to change in sonar calculation with new upgrade).
Discussed remaining JIRA items in great details → portal-151
(assign priority from items in wiki page to JIRA by Leimeng)
MUSIC integration - add JIRA epic/US - Sunder to provide the % complete
Development is targeting to complete by 02/28
Leimeng to coordinate a meeting to share the MUSIC integration details with testing teams to plan the test strategy for these features.
AAF, if AAF is not ready for testing by 2/15, then Portal will not integrated with AAF for Beijing release - Leimeng send email to Sai - Is the AAF instance ready in LAB env to test the integration?
Defect tracking of Critical and Highs - Naveen and Shireesh to coordinate with Leimeng to test and close them and raise as concern if cannot be closed.
Beijing Release Planning:
M0 - dev kick-off, Nov 16
M1 - planning Jan 16
M2 Functionality Freeze Feb 12, 2018 → fill in the contents by Manoop & Leimeng
M3 API/Data Model Freeze Mar 8, 2018
M4 Code Freeze Mar 29, 2018