Policy R1 - RC0 Deliverables for Release Candidate Milestone Checklist Template

The following items are expected to be completed for the project to Pass the Release Candidate Milestone.

This template must be filled out for every Release Candidate Milestone (RC0, 1, 2, x)

RC Release Candidate Milestone overview is available in wiki.

Practice Area

Checkpoint

Yes/No

Evidences

How to?

Practice Area

Checkpoint

Yes/No

Evidences

How to?

Product Management

Are all tasks associated with the release been marked as "Done" in Jira?

No - In Progress

Getting issues...
- These are all the Tasks marked as Closed and Resolved

Getting issues...
- These are all the Tasks marked as NOT Closed or Unresolved

  • We have closed by EOB Wednesday Oct 11, 2017 most tasks that we were doing for RC0

  • We still have open tasks related to integration testing that is currently still happening.





Have all findings from previous milestones been addressed?

Yes





Development

Have all Defects of priority Highest and High been in status "Done" in Jira?

Yes

Getting issues...
- These are all the bugs of highest/high priority that are marked as Closed and Resolved

Getting issues...
- These are all the bugs of highest/high priority that are NOT marked as Closed or Unresolved

  • This bug is APPC - will verify it and close it 10-11-2017





Are all JIRA issues used as a reference in a commit in status "Done" in Jira?

Yes



Very often, some JIRA issue remains in status "Todo" in JIRA while the commit they are referenced to is successful.

Is there any pending commit related to Highest and High priority issues older than 36 hours in Gerrit? In case there are messages going back and forth between authors and reviewers, it is acceptable to be above 36 hours.

No

https://gerrit.onap.org/r/#/q/status:open+projects:policy



Are all the Jenkins jobs successfully passed (verify + merge jobs)?

Yes

https://jenkins.onap.org/view/policy/job/policy-common-master-verify-java/

https://jenkins.onap.org/view/policy/job/policy-common-master-merge-java/

https://jenkins.onap.org/view/policy/job/policy-drools-applications-master-verify-java/

https://jenkins.onap.org/view/policy/job/policy-drools-applications-master-merge-java/

https://jenkins.onap.org/view/policy/job/policy-engine-master-verify-java/

https://jenkins.onap.org/view/policy/job/policy-engine-master-merge-java/

https://jenkins.onap.org/view/policy/job/policy-drools-pdp-master-verify-java/

https://jenkins.onap.org/view/policy/job/policy-drools-pdp-master-merge-java/



Has the team delivered all their release artifacts in Nexus Releases repo?

There should be at least ONE version of each artifacts available in Nexus Releases repo.

Yes

Staging artifacts were available.

Refer to Independent Versioning and Release Process for procedure

Integration and Testing

Have all CSIT Use Cases (created by each project team) passed?

Yes

https://jenkins.onap.org/view/policy/job/policy-master-csit-health/



Is there a Docker images available for each repository?

Yes

Docker staging images were available.



Has the project code successfully passed the Daily Build process?

Yes



Goal is to ensure the latest project commit has not broken the Integration Daily Build 

Documentation

For RC0, for project delivering binaries, has the team populated and validated all the sections of either the Platform Component or SDK template?



Yes

There are only a subset of the suggested Platform Component list that are applicable to policy:

http://onap.readthedocs.io/en/latest/submodules/policy/engine.git/docs/index.html



Most teams have already created the high level file structures in readthedocs, and populated some actual documentation. However, the remaining sections of the appropriate teamplate must be completed.

Platform: A&AI, APP-C, CLAMP, CLI, DCAE, DMaaP, Holmes, MSB, OOM, Policy, Portal, SDN-C SDC, SO, UseCase UI, VFC, VID

SDKs: AAF, CCSDK, External API Framework, Multi VIM/Cloud, VNFSDK

For RC1, has the team addressed any issue (recorded in JIRA) provided by the Documentation team?

n/a





For RC2, for project delivering binaries, has the team populated and validated all the sections of the Release Notes template?

n/a





For RC2, has the Documentation Team provided the final approval for your project documentation?

n/a