Date
Meeting Logistics
Day | Time | Meeting ID | Zoom Link | Join by phone |
Monday | [sdc] Team ONAP3, Mon UTC 11:00 / China 19:00 / Eastern 06:00 / Pacific 03:00 | https://lists.onap.org/g/onap-meetings/calendar | See Groups.io calendar invite | See Groups.io Calendar Invite |
Meeting Attendees
Agenda & Minutes
Review open action items from last week
Agenda | Minutes (Draft to be updated during call) | Slides |
High Priority Bugs | High priority defects :
| |
Open review | ||
Kohn timeplan |
Kohn timeplan has been approved by TSC. M0 was last Thursday 7th Apr
Kohn timeplan to be revised due to changes in Jakarta timeplan and holiday in some countries on 6th May . M1 (General requirement approved) proposed to be moved from 26th May to 9th June, M2 proposed to be moved to 30th June
Release plan updated: Release Planning: Kohn M1 moved to 9th June. Release management tasks published: - SDC-3992Getting issue details... STATUS M2 moved to 14th July
M1 moved to 23rd June. M2 moved to 14th July
M2 scheduled for this Thursday 14th July. Tasks to complete: - SDC-4068Getting issue details... STATUS
M2 postponed by one week to Thursday 21st July
M2 conditionally approved by TSC last Thursday
M3 scheduled for 1st September
M3 postponed one week to 8th September
M3 and M4 scheduled for this Thursday 22nd Sept
M3 passed last Thursday (22nd Sept) M4 postponed to this Thursday (29th Sept). RC also pushed out one week to 27th Oct. Sign off date remains the same (10th Nov)
M4 postponed to today, Monday 3rd Oct Latest Kohn functional build (1.11.9) merged into OOM https://gerrit.onap.org/r/c/oom/+/131325 Branch created for Kohn bug fixes. Creation of associated Jenkins jobs in review https://gerrit.onap.org/r/c/ci-management/+/131326)
M4 approved by TSC last Thursday 6th Oct RC planned for Oct 27th
RC planned for this Thursday 27th Oct - tasks to be completed: - SDC-4197Getting issue details... STATUS | |
London timeplan | Draft time plan for London:
Timeplan for London approved by TSC last Thursday. Kickoff scheduled for Oct 20th
London Kickoff was last Thursday. Next milestone M1 (global req. approval on 1st Dec) | |
London impacts | Continuation of support for TOSCA functions Constraint Validation Viewing of data types in UI | |
Bugs | Open bugs: 37 (up 2)
| |
Multi-tenancy |
Documentation and code reviews to be shared when ready. Documentation to be added in SDC wiki, with readthedocs to be updated when implemented
Architecture committee have requested the proposed solution be presented
Demo to be presented next week Request for review sent to Architecture Committee, waiting for response
Architecture review tomorrow - ONAPARC-753Getting issue details... STATUS
Arch Comm review took place last week. The proposed approach was acceptable to the architecture committee, however they recommended pairwise discussions with other components such as A&AI, SO, DCAE to align on an overall solution |
Action Items