SDC 10/24/2022 weekly meeting agenda

Date Oct 24, 2022 

Meeting Logistics

Day

Time

Meeting ID

Zoom Link

Join by phone

Monday

[sdc] Team ONAP3, Mon UTC 11:00 / China 19:00 / Eastern 06:00 / Pacific 03:00

https://lists.onap.org/g/onap-meetings/calendar

See Groups.io calendar invite

See Groups.io Calendar Invite



Meeting Attendees



Agenda & Minutes

Review open action items from last week

Agenda

Minutes (Draft to be updated during call)

Slides

High Priority Bugs



High priority defects :

 

type key summary assignee reporter priority status resolution created updated due
Loading...
Refresh



Open review



Kohn timeplan

Release Planning: Kohn



Apr 11, 2022 

Kohn timeplan has been approved by TSC.

M0 was last Thursday 7th Apr

Apr 25, 2022 

Kohn timeplan to be revised due to changes in Jakarta timeplan and holiday in some countries on 6th May . M1 (General requirement approved) proposed to be moved from 26th May to 9th June, M2 proposed to be moved to 30th June

May 30, 2022 

Release plan updated: Release Planning: Kohn

M1 moved to 9th June. Release management tasks published: SDC-3992: Global Requirements ApprovalClosed

M2 moved to 14th July

Jun 20, 2022 

M1 moved to 23rd June. M2 moved to 14th July

Jul 11, 2022 

M2 scheduled for this Thursday 14th July. Tasks to complete: SDC-4068: Specification FreezeClosed

Jul 18, 2022 

M2 postponed by one week to Thursday 21st July

Jul 25, 2022 

M2 conditionally approved by TSC last Thursday

Aug 8, 2022 

M3 scheduled for 1st September

Sep 5, 2022 

M3 postponed one week to 8th September

Sep 19, 2022 

M3 and M4 scheduled for this Thursday 22nd Sept

Sep 26, 2022 

M3 passed last Thursday (22nd Sept)

M4 postponed to this Thursday (29th Sept). RC also pushed out one week to 27th Oct. Sign off date remains the same (10th Nov)

Oct 3, 2022 

M4 postponed to today, Monday 3rd Oct

Latest Kohn functional build (1.11.9) merged into OOM https://gerrit.onap.org/r/c/oom/+/131325

Branch created for Kohn bug fixes. Creation of associated Jenkins jobs in review https://gerrit.onap.org/r/c/ci-management/+/131326)

Oct 10, 2022 

M4 approved by TSC last Thursday 6th Oct

RC planned for Oct 27th

Oct 24, 2022 

RC planned for this Thursday 27th Oct - tasks to be completed: SDC-4197: Release CandidateClosed



London timeplan

Draft time plan for London:

Release Planning: London

Sep 26, 2022 

Timeplan for London approved by TSC last Thursday.

Kickoff scheduled for Oct 20th

Oct 24, 2022 

London Kickoff was last Thursday. Next milestone M1 (global req. approval on 1st Dec)



London impacts

Continuation of support for TOSCA functions

Constraint Validation

Viewing of data types in UI



Bugs

Open bugs: 37 (up 2)



key summary type created updated due assignee reporter priority status resolution
Loading...
Refresh



Multi-tenancy

Jul 11, 2022 

Documentation and code reviews to be shared when ready. Documentation to be added in SDC wiki, with readthedocs to be updated when implemented

Jul 18, 2022 

Architecture committee have requested the proposed solution be presented 

Sep 5, 2022 

Demo to be presented next week

Request for review sent to Architecture Committee, waiting for response

Sep 26, 2022 

Architecture review tomorrow 

ONAPARC-753: (London-R12 Tentative) - CompReview - Multitenancy implementation on SDCClosed

Oct 3, 2022 

Arch Comm review took place last week. The proposed approach was acceptable to the architecture committee, however they recommended pairwise discussions with other components such as A&AI, SO, DCAE to align on an overall solution





Action Items

 



Slack Channel: #SDC on LFN ONAP.org Slack instance (onapproject.slack.com)



Recording



Chat