Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 16 Next »

Release Schedule 

Approved by the TSC on August 26, 2021 (r5)


Activity Log

DateEvent or UpdateMilestones Affected
Sept 9Remaining M3 items closed M3
Sept 2TSC approved M3, conditioned on completion of remaining milestone tasks by M4M3
Aug 26TSC approved one week slip to M3.  No other milestones affected.M3
Jun 23M2 approved by TSC, with exceptions, by email vote.M2
May 20M1 approved by TSC, with exceptions.  Details here.M1
May 10Added ONESummit dates to the schedule (r4) for reference.  (No changes to Istanbul release milestones from r3)None
May 6Approved by the TSC (r3)ALL
May 4

New proposal (r3) in response to feedback at May 3 PTL meeting

  • Collapsed 3 RCs into a single RC
  • Added more time from M4 to RC
  • Added an additional week between RC and sign off
  • Corrected dates for China National Day holiday. Should be 10/1 -8, instead of 9/27 - 10/1.
RC0, RC1, RC2
Apr 28New proposal (r2) in response to feedback from original proposal.M1 - Sign Off
Mar 18Proposal presentation to TSC.  Requested approval of just the kickoff date of April 1.  Other milestones to be discussed at a later date.  TSC approved kickoff date ONLY.M0
Mar 11Proposal presentation to TSC. TSC expressed concerns about the second half of the release occurring during the summer, which could conflict with summer holidays.  Proposal not approved.ALL
Mar 10Second draft
  • Added a new milestone  before M3
  • Previous "M3" becomes M4
  • Added event in June
  • Moved Honolulu sign off to April 8
Mar 4Initial draft postedN/A
  • No labels