Skip to end of metadata
Go to start of metadata
You are viewing an old version of this content. View the current version.
Compare with Current
View Version History
« Previous
Version 20
Next »

Release Schedule (Approved Dec 10, 2020)

Activity Log
Date | Event or Update | Milestones Affected |
---|
Feb 25 | TSC determined that there is insufficient information to make decision, so M3 pushed out 4 days to March 1 | M3 |
Feb 1 | Uploaded ONAP Honolulu r1 to show changes to M1 and M2 dates | M1, M2 |
Jan 25 | M2 approved with exceptions | M2 |
Jan 21 | Requirements not met. M2 slipped to Jan 25 | M2 |
Jan 14 | M1 approved with exceptions | M1 |
Jan 11 | Requirements not met. M1 slipped to Jan 14 | M1 |
Dec 10 | TSC approved schedule | ALL |
Dec 10 | M1 moved out 4 days to Jan 11 | M1 |
Nov 20 | Second draft posted |
|
Nov 11 | First draft posted |
|