Topics:
SO needs to update RC1 score, Frankfurt Release Requirements, 2: Frankfurt Release Integration Testing Status
Project Status in Frankfurt Release
Meeting recording:
Frankfurt Release Integration Test Blocking Issues
Integration Weather Board for Frankfurt Release
Review
ARC Service Orchestrator Component Description - Frankfurt
Branch cut awaiting the resolution of the blocking issues.
Requirements | M1 committed Requirement details | M4 preparedness Status |
SO-2556 | Migrate PNF PNP workflow to Building Blocks | Risk on completing by Feb, decision point API has dependency that is not yet resolved. Backup plan: The existing flow is intact and we will switch back to the existing code till the new changes are merged. For F release we will continue with what we have. For F release looks like the backup plan would be defaulted for PNF Config Assign, Config Deploy. This functional aspects would be checked in parallel and would be included in the master branch. 11-03: Testing is in progress and the master release is being verified, found a new error in the Workflow executor related to the inventory "No PNF found" investigating further. This is a blocking issue for the PNF flow to be complete. need to verify with the new AAI and the input params. 15-04 : Testing it with the Robot scripts to test the E2E testing, no blocking issues. Model related parms were found with some issues that would need to be handled in the G release. |
SO-2519 | S3P - Improvements of Service Orchestrator | Need to revisit based on the badging demands |
SO-1579 | SO supports ETSI SOL005 Alignment of its interfaces with NFVO | Expected to finish code review by next week. Yet to start Module level testing. Need to rebase the code and provide a new commit including all the related changes, ETA this week. Code Merged to the master and would be cut to the F branch, fine tuning is requried to increase the testing. The code is in the adaptation and would not impact the key flows. 11-03: Standalone testing is in progress, need to perform the integration testing on the windriver lab. Testing will happen with VFC. 15-04 : |
SO-2432 | Multi-domain Optical Network Service Orchestration Support in SO | This week expected the code review. Module level is in progress. So code is submitted for review. Need to re-submit the code the current changes seems to have issues and bring additional complexity. Cant be included in the F release branch, so will try take it as PoC and after review include in the master for the next release. XinMiao agrees to this approach. 11-03: Scope is reduced to bare minimal , there is no dependency with other modules of ONAP (SDC, AAI and OOF). There will be no optimization as the selection of the best possible for now. This will be the basic functional feature provided for the F release, will be extended further to the expected feature in the G release. To ensure the existing functionality not to be broken and verify in the CMCC (CCVPN) , Swisscom (BBS), Windriver (Integration) and the Orange (MDO) labs. To work wit the Usecase leaders to ensure there is no impact. ; 15-04: Verified in the Swisscom lab for the BBS, 5G slicing is being tested by the CMCC in their lab. CCVPN tested in the local need to check the SOTN on the UNI ... |
SO-2427 | SOL002 Adapter - supports EM-triggered VNF/VNFC Management | SO-2428: SO changes merged.
11-03: Demo ready. 02-04: Release notes description: Ve-Vnfm Adapter (aka SOL002 Adapter) registers in external VNFM for VNF LCM notifications (ETSI SOL002 v. 2.5.1) Ve-Vnfm Adapter (aka SOL002 Adapter) sends DMaaP events based on ETSI VNF LCM notifications received from external VNFMs (ETSI SOL002 v. 2.5.1) 15-04: Demo is provided last week, the code is merged. CSIT testing in progress and we need it to be checked if pushed by G release. |
SO-2404 | SO Catalog Management Support | No risk, code by this week, testing to be completed. For F release we noticed to have some non-functional issues, working on the alternatives, need to check if this could be moved to the ESTI catalog manager for G release. Dependency on the SDC for the ETSI type if possible.
11:03: ready for the Integration testing. Change: Support of ETSI Catalog management among the SDC - SO SDC Controller - ONAP-ETSI Catalog Manager.
15-04: Found a issues on the catalog mgr and informed to the VFC team, its to be checked. E2E testing will be tested after this patch is applied. |
SO-2368 | Support 5G slice orchestration | working on OOF integration part, Final integration testing of OOF. This week the coding is targeted. Testing will continue next week, have dependency on OOF. AAI 1.6.4 is released and unblocked for the code to checked in , would be done by EOD today. UT is in progress and expected to be completed by next week. Testing would be conducted in the CMCC and windriver lab with the simulator in place. 11-03: All changes are merged , testing started in CMCC Lab. 15-04: No blockin issue reported, SO oof integration is in progress. Dependency on the OOM changes for the NSSMF adapter that needs to be merged. |
SO-2281 | SO support of Network Slicing Demo in Frankfurt | Demo will follow the same as above. Last week the demo has been addressed. - Closed |
SO-2156 | ETSI Alignment Support - SOL003 Adapter Enhancement for Frankfurt | No risk, testing in progress, and it will be done before March 2nd. TLS between SOL003 Adapter and SVNFM could be moved to the G release.
11:03: ready for the Integration testing. certificates from MSB are being updated and tested. Change: SOL003 Adapter Enhancement for Frankfurt
15-04: Found a issues on the catalog mgr and informed to the VFC team, its to be checked. E2E testing will be tested after this patch is applied. CSIT testing is in progress, the issue in on the F release. |
SO-2087 | AAI update for VNF improvements | |
SO-2086 | SO Multicloud plugin to Multicloud improvements | Testing effort, will need to take it as per the need. Https call to the MC. dependency on the changes of the MC. Plan to complete this by next week. Should ensure the openstack part of the code is not impacted. Build failure of SO and the oom patch update needs to be corrected for the msb input. 11-03: MSB changes are merged in OOM for the HTTPS config. Testing is in progress. MC is in progress of HTTPs movement. 15-04: Testing is in progress, the env is being setup. Intel Windriver lab is being setup with the env. |
SO-2046 | support Java 11 upgrade | The initial analysis is done. the code is being done in a separate branch and testing is in progress for the vFW usecase. Oparent should be 3.0.0 Java SDK should be the one from Integration team. Deferred it G release. Will continue the work and merge to the master. Att is doing an internal PoC on the migration will take the inputs. |
TSC must have | SO code coverage after the migration to sonar cloud is 64% - PASS SO/libs - 67% - PASS All Http port to migrate to the Https: Waiver for the 30227 port is granted 30224 is fixed Vulnerabilities fix - So/libs -Done 15-04: Issues have been addressed, the issues need to be addressed. | |
Issues open :
Discussion: