Discussion items

TIME FOR THIS MEETING WILL BE 2PM UTC = 10AM EST (USA); 7 AM PST (USA)

ItemWhoNotes

Discussion this week

 

All in 5G U/C


  1. VES Spec updates DCAE project next week to discuss how to proceed. Need to make sure it is one w/ the correct content. DRAFT 4.  Alok G. is on medical leave, and Albino Pinho / Trevor Lovett is the current delegate. PM schema update needed. Security change. Trevor has sent out a review. CRs are posted. Does not include the Fault & CMNotify (will be in VES 7.2 which is in R7). Gerard Hynes pulling in VES experts. David Kinsey looking at Harmonization options. David Smith (ATT) Jean-Michel Corneley (Orange) to discuss options for Harmonization. Should happen before DCAE call. From Ericsson Oskar Malm has forwarded. Gerrit Review open for VES event listening & VES registration. Pulling these documents into READTHEDOCs: https://onap.readthedocs.io/en/latest/submodules/vnfrqts/requirements.git/docs/Chapter7/index.html . Re-reviewing the deltas from last Red the docs updates. Review open until Fri Feb 7 2020. deltas from Dec 10, 2018. CMNotify NOT in version associated with R6. Gerrit Review: https://gerrit.onap.org/r/dashboard/self 
M4 Deadline Deliverables

All in 5G U/C

M4 Deliverables DEADLINE 

R6 Frankfurt Release: Frankfurt Milestone Status

Release Planning Page: Release Planning

M1 Deliverables Checklist: Deliverables for Planning Milestone Checklist Template

Deliverables by Milestone: Frankfurt Deliverables by Milestone

(1) FUNCTIONALITY FREEZE -

M2 MILESTONE: Functionality freeze

No new visible functionality is to be added to the current ONAP release.

A stable document describing the API is documented and available in wiki.

Base set of impacts to VNF Requirements identified by use case/ project.

(2) API & DATA MODEL FREEZE -

M3 MILESTONE: API & data model freeze.

Mark the end of API and Data Model change. API and Data Model are now Frozen.

Any changes to the API must be brought to the knowledge of the TSC for review and approval.

50% of Functional Test Case are automated.

(3) FUNCTIONAL TEST CASES -

Functional Test Cases are defined & documented


M2/M3 CHECKLIST:   Release Planning (legacy)

  • (1) Functionality freeze, no new visible functionality is to be added to the current ONAP release.
  • (2) Functional Test Cases - Each Project team has defined & documented Functional Test Cases.
  • (3) API Documented - A stable document describing the API is documented and available in wiki.
  • (4) VNFReq - Base set of impacts to VNF Requirements identified by use case/ project.
  • (5) Release Status - Update M2 scorecard Frankfurt Release Requirements
  • API docs complete - Where?
  • Data Models (e.g, JSON, YANG, Swagger, etc.) shared with Modeling/Community
  • Architecture Review complete (if required)
  • No Gerrit requests older than 36 hrs.
  • Provide docker to integration testing for Wave1: oParent, PortalSDK
  • OOM port list update
  • Fix any Integration blocker - Daily status updates on integration blockers, Highest/High issues
  • Review and plan resolution of any License scan, security issues
  • Update Frankfurt Risks


(CONTINUOUS) - DOCUMENTATION - Documentation (Read the Docs) - M1 - M4

CONFERENCES & DEMOSAll in 5G U/C

ORAN/ONAP Plugfest held Thurs Dec 5, 2019 (AM EDT UTC-4 USA) at Rutgers WIN Lab (Brunswick NJ).

Official WIKI Site: https://wiki.o-ran-sc.org/x/egBv

RECORDING OF DEMOS PLUGFEST

https://zoom.us/recording/play/jbp0ivv4Cs0RwyWM1YiIqHDMXWvnwxCH-Xwh3PCezteHdg_5TRBGmGX-tnvvv4ze?startTime=1575556625000

CONFERENCE

  • Jan 13-16, 2019 Prague DDF -
  • LINK to presentations & presentation proposals
  • PROPOSALS : https://wiki.lfnetworking.org/display/LN/Call+for+ONAP+DDF+Topics+-+Prague+2020
  • SCHEDULE:

    DEMOS PLUGFEST

    https://

    wiki.lfnetworking.org/pages/viewpage.action?pageId=25364127


    CONFERENCE

    PLUGFEST

    CONFERENCES

    April 22-24 Open Network & Edge Summit (ONES) - Los Angeles - GuiLin R7 (Planning).

    Early June DDF - Asia (GuiLin R7)

    ACTION: Will remote presentations be possible, links to remotely attend? When is final schedule up.

    RunTime Config DB


    Architecture S/C presentation for Run Time DB.

    Team is working to define the Proposal (see wiki).

    Then it will be presented at the Arch S/C and then TSC.

    Sync with Sandeep - will meet with Sandeep Fri 7 2020. Ted Johnson. Existing interface.

    For R6, will be part of CC-SDK. Met with Yuriy Malakov  & Dan Timoney . 5G CONFIGURATION (RunTime DB) not a separate component in R6.

    CMNotify - The DCAE, CMNotify VES event (proper) are pushed to R7

    • STEP 1 GENERATE: xNF (RAN Simulator) GENERATES a VES CMNotify - Wipro SON (R6)
    • STEP 2 RECEIVES: DCAE VES Collector RECEIVES the CMNotify - Nokia (R7)
    • STEP 3 DCAE: DCAE PROCESSES Event- Nokia (R7)
    • STEP 4 DMaaP: DCAE PUBLISHES onto DMaaP - Nokia (R7)
    • STEP 5 LISTEN: CCSDK (Controller) LISTENS to DMaaP - SandeepShah (R6)
    • STEP 6 RTCfgDB: RTCfgDB UPDATES with info - SandeepShah / Techmahindra Devendra Chauhan (R6)

    Feb 3-7 Nokia has confirmed that Step 2/3/4 is in R7 due to VES review.

    Network Slicing R6 Proposal

    Update on slicing proposal. SO/Seshu presented.

    Multiple functional requirements/Use Cases. Recursive orchestration of nested services. Didn't want independent W/F for flows but try to leverage/reuse work. Presented the End to End U/C with macro-view for E2E slice. and components impacted. Right now impact will be on SO, OOF, Policy, SDC and AAI. What controller will be used for managing slices? Focusing on design aspects and instantiation and activation. Put up logical E2E slice. Target simple VNFs. Focus to create VNF vs reconfiguring a VNF? Slice segments are going to be both dedicated/shared. Started with discovering existing resources; assume segments created with VNF/PNFs in inventory & discoverable. Spinup new slice instances.

    :

    • (1) ROADMAP - Proceeding with detail, developments for roadmap beyond R6.
    • (2) API - defining API in progress.
    • (3) PoC - Prototype of PoC from Orange focusing on VNF-portion.
    • (4) SO - Implementation in SO W/F and hierarchy using Svc ref concept to be discussed beyond R6.
    • (5) ORCHESTRATION - documentation what will ONAP do wr.t. slice orchestration
    • (6) MODELING - Discussing Modeling aspects, how to represent CSI, NSSI, NSSMF etc how to implement in SO how to communicate w/ external domain NSSMF.
    • (7) VID - Discussion: Milind Jalwadi (Unlicensed)
      • JSON based screens for VID, Is there a slicing GUI that could be re-used.
      • would want to upstream that NSST NSSD
      • Part of the Network Slicing Use Case.

    Presentation/slides at: NETWORK SLICING PoC in R6 Frankfurt (Obsolete)


    ORAN/3GPP ONAP Harmonization U/C

    Trying to settle on scope of the Use Case. List of many possible contributions that will take more than one release to complete. Impacts for items to be added to wiki (analysis).

    Prioritize the work items what we could propose to accomplish.

    CM Notify as a new domain has been accepted on the DCAE S/C today Oct 24 2019.

    Dongho Kim  will be creating the test/integration page.

    - A1 & O1 test integration pages have been added & links. DongHo Kim leading the Integration

     Sandeep code was merged w/ SDN-C branch. Current container has the latest code. Continuing to test. In AT&T lab now being tested

    •  marge.hillis will setup a call to discuss possibly some gaps maybe move things to R7. Meetings w/ Dave Smith et al. trying to push through harmonization. Standards meeting in Nov. 2019. There was push back & negotiation between 3GPP & ONAP as to how to proceed. This is because it was first exercise, once we have a process in place it should go more smoothly. 3GPP specified some stuff and tried to over-specify into ONAP. Shortcoming in 3GPP current CMnotification only handles one MO if this was adopted. Working with 3GPP to correct. Waiting to see if 3GPP will accept the proposal. Working w/ standards for 3GPP FEB SA5 standards meeting.
    •  Harmonization U/C - Some things pushed out (Partial Green) at M2/M3 - O1 enhancements moved to G release hoping to harmonize (1) Fault & (2) Config change Notification (CMNotify) Thus CMNotify will be pushed to R7.  Meetings to harmonize 3GPP standards. Waiting for Standards to be Harmonized. Intentionally descope something so that we don't cause churn. Don't want to implement something that would have to be re-implemented. Don't want to implement something that would have to be re-implemented. Trying to get VES SMEs engaged. But won't make R6 because of the timeframe. The VES Specs does need to be updated (see next point). Trying to align ORAN, ONAP & 3GPP aligned.
    •  ONAP 3GPP CONVERGENCE MEETING  - Dave Kinsey didn't agree option that was optimal wanted to discuss option he proposed. Wanted to bring in VES ppl to look at options. David Smith created & leading the meeting. Should invite Oskar Malm, Cormac Mullally, Mark Scott. Looking at options to populate the common header such that events w/ opaque payload can be fwded to correct DMAAP topic. to harmonize ONAP different standard standards defined things.
    •  CMNotify for PoC/Demo - R6, OOF-SON-PCI & the RunTime Config DB U/C needed the CMNotify, Sandeep Shah said they had a simulation of CMNotify for demo purposes.
    •   INTEGRATION - Need update from Dongho Kim for A1 interface.
    OOF SON PCIN.K. Shankaranarayanan

    From SDN-R when we send config change align to NetConf Yang model avail. whatever yang model used, want config DB schema to be aligned w/ yang model to keep model driven. wanted Yang Models from ORAN if possible. In license catch-22. Some yang models for RAN on ORAN website due to licensing issues from Martin Skorupski took 3GPP model converted to files to compile. Issue w/ ORAN getting ok from 3GPP that it is a valid rep of 3GPP model. Option (1) use previous yang model, or (2) switch to ORAN model if available immediately. yang to SQL schema. Only need some parts of the model for SON project. Currently MariaDB continue to use. Piotr, Marek, et al. If there are useful file wo/ IPR issues, should be a way to use interim files.

    WoW w/ Model & Arch

    Way of Working between Architecture , Modeling Subcommittee & Use Case Teams and what happens and touch-points at M0/M1/M2/M3.

    Process for Modeling WoW and development with Architecture & Modeling.

    Proposed ONAP Release Process Updates for Information and Data Modeling

    Use Case Template

    Use Case Template - discuss updating the Use Case template & pages with some of these fields. Modeling team has said it would be useful for them to have the pre-condition & post-conditions, and information being passed (info-flows) documented.

    Proposed Functional Template for Use Cases (driven from MEF/TM Forum) - showing interactions & information flows.

    Use Case Template

    Filling out, describing and creating the Wiki for a Use Case

    Use Case Tracking Template and Use Case Template

    Ben talked w/ Andy Mayer U/CR call Oct 23. He said he is preparing the page, and would present here at the 5G U/C S/C call.

    REQUIREMENTS SUBCOMMITTEE - requirements sub-group / not bring use cases any more, refer to them as requirements. / proposed change talk less about architecture in requirements mtgs & reviews. more clear split between req & arch discussion.   / Alla Goldberg changed U/C S/C to Requirements S/C. Security and ctl loop req will be discussed in those S/C; other things should go to Req S/C.

    Monday - - what input for Req review; should not go into realization aspects should be moved out of req review. What type of info & how much info at M0. when just reviewing proposed req. Andy has said Proposed Functional Template for Use Cases this is ready to go live.

     , PM Dictionary, 5G NRM

    5G U/C teams

    Chaker Al-Hakim - History Inventory resources associated w/ xNF. Assumptions: what are the resources that I need to inventory about a xNF so that I have a complete view of the VNF. parms added due to nature of VNF. resource inventory didn't have to do with provisioning data that the xNF can have. Should be evolved to reflect what we know today.


    PNF Pre-onboarding/ onboarding

    PNF U/C teams

    Benjamin Cheung


    PNF / SW Upgrade

    Zu Qiang

    Reviewed with SO team.

    Preparing for DDF. will discuss with Change Management team, might be presenting. R6 in progress.


    5G/ Bulk PM


    Preparing presentations at DDF in Prague in DDF for R6 BulkPM functionality in Jan 2020.

    Demo in Dec 5, 2019 - R4 functionality. PM control part is green; the other bulk PM for certificate handling has dependency with

    Jira Legacy
    serverSystem Jira
    columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
    serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
    keyREQ-140
    PNF / NetConfOskar MalmBasic U/C unchanged, support for NetConf over TLS. What is being worked on in R6 is to have a improved functionality around certificate handling. When you have a TLS 1.x for authentication for ONAP so the NF when it connects to ONAP it is a valid xNF. Authenticate user cert ONAP needs to get the certs from somewhere - a centralized solution w/ AAF. and connect to ext. PKI via CMPv2. ONAP component minimum version TLS 1.2. Dependency to REQ-140
    PNF / Plug and PlayBenjamin Cheung

    held meeting for discussing Civic Address elements & Geolocation information w/ the modeling S/C

    PnP - PNFD/SDC AID/AAI Schema Modeling - Discussion Jan 2, 2020

    Eventually will the PNFregistration VES event for PnP (R7).

    SO presentations related to Building block definitions. Dependency to REQ-140. Option #2 new arch. is agreed. Option #1 continue w/ old.

    R6 Use Case VS RequirementsAll in 5G U/C

    TSC Release Page.

    Frankfurt Release Requirements

    WHAT IS A USE CASE VS A REQUIREMENT? In the REQUIREMENTS Table of the R6 Release Requirements Wiki (above) the Use Case requirements as discussed on the TSC call for Sept 12, and David McBride has asked that we have requirements (jiras) on separate rows. Further follow-up discussions will be had for "what is a use case" and if some of the 5G use cases should be moved up to the first table.

    5G Service Modeling U/CBenjamin Cheung

    WIKI: 5G RAN SERVICE MODELING & DEFINITION in R6 Frankfurt

    CDS Data dictionary - Define attribute, in that entry tells you how to get that value. Yuriy Malakov

    If you needed the IP@ you can go that entry → points to the REST call. Used for instantiation and configuration management. Model driven ONAP. Modeling Concepts

    3GPP TS28.541/TS28.540 - 5G NRM Network Resource Model analysis (spreadsheet). Looking parameters introduce

    Classify parameters - CDS Data Dictionary, A&AI, RunTime Cfg DB.

    Presentations - Modeling S/C, U/C S/C, U/C Realization, 5G U/C.

    Modeling S/C - Experimental info model introduced (standards driven)

    A&AI - classification of A&AI parameters. Commission (might need at installation & commissioning) → A&AI.

    Onboarding - Onboarding, PNF PNFregistration, CMNotify (VES events), Pre-defined "load 3GPP model"

    Information Flows - Where these might be used.

    ORAN Standards - Usage of the 3GPP TS28.541 in ORAN Standards. Might want to consider which 3GPP parameters ORAN cares about & when. They might an opinion of when to incorporate parameters.

    Presentation at Use Case Realization call  

    Use Case Realization Call: January 29, 2019 - next step to present to Modeling S/C.

    CMPv2 Security (AAF enhancements)

    Pawel Baniewski

    Hampus Tjader

    M2/M3 CMPv2 & AAF status - CMPv2 GREEN at M2/M3 right now. 

    Jira Legacy
    serverSystem Jira
    columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
    serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
    keyREQ-140
    have committers now. AAF S/W. CMPv2 protocol.

    1. REPO Avail - Nokia has created a repo, discussing architecture now.
    2. Access - Confirmed, we can access the Repo.
    3. Deliveries - Nokia planning to deliver the CertService (accept request from client), CertService Client (init container w/ ONAP apps), and integration with external CMP v2 service.
    4. Integration to Border Components - Integration with ONAP modules, DCAE/VES, SDNC, DCAE/DFC very likely to be post-posted to R7. High Risk The ONAP "bordering" components. Consequences - in scenario where you int ONAP w/ external function won't be able to dist cert generated in external Cert. Authority (CA) within ONAP; thus would still be able to integrate a NF to ONAP but would need to distribute manually bring the certs to ONAP. The Automation of distribution would be missing. The NFs contact the CAs to get certs. Integrate ONAP w/ CMPv2 w/ CertSvc to same Ext. CA. Integrate the xNF gets the cert to Ext. CA. ONAP gets matching trust anchors from same Ext. CA, loaded to an ONAP component. CertSvc bought back dist. within ONAP volume where cert is stored & consumed by ONAP component. 3GPP requires/originated. Consumes maximum of what 3GPP has.
    5. Slides -
      Jira Legacy
      serverSystem Jira
      serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
      keyONAPARC-553
    6. Integration - Separate integration efforts. 140 is the common part in AAF, including client component that can be reused, there is integration work which have separate requirements. This creates a dependency on those other requirements, being delivered with enough time to do integration.
    7. Plug and Play, Bulk PM, NetConf - CMPv2 PnP got descoped, secure Bulk PM is descoped, NetConf is proceeding see: Frankfurt Release Requirements
    8. REQ-76 - If we manage to complete the integration into SDN-C (REQ-76) additional integration related to that.
      Jira Legacy
      serverSystem Jira
      columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
      serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
      keyREQ-76
    9. DEMO - Plugfest in June 2020 it might be nice to demo something.

    ...