- OOM Casablanca - M3 Architecture Review completed was completed August 21st
- the review attempted to socialize our commitments for M4, based on current status of assigned work in Sprint
- OOM Casablanca - M3 API Freeze Milestone Checklist due is due Thursday - August 23rd
- please help to clear out overdue reviews: https://gerrit.onap.org/r/#/q/project:oom+and+status:open+and+age:36h
- Dublin Planning
- encouraging community to add requirements to OOM Requirements Gathering for Release Planning
- Encourage community to add requirements to above wiki as soon as possible - Dublin planning to start shortly
- Community reviews will start in a week or two
- ~ only 4 weeks before next week
- Dublin scoping will start next week in parallel with Casablanca development
- Review work in progression current sprint: Casablanca-1 (ends 08/22)
- only 4 weeks of development time remaining!!
- Code Freeze September 20