OOM Meeting Notes - 2018-08-22
Agenda
OOM Casablanca - M3 Architecture Review was completed August 21st
the review attempted to socialize our commitments for M4, based on current status of assigned work in Sprint
OOM Casablanca - M3 API Freeze Milestone Checklist is due Thursday August 23rd
please help to clear out overdue reviews: https://gerrit.onap.org/r/#/q/project:oom+and+status:open+and+age:36h
Review work in progress for current sprint: Casablanca-1 (ends 08/22)
only 4 weeks of development time remaining!!
Code Freeze September 20
please help to pick up any stories and defects that are marked for Casablanca and are not currently assigned
Helm Chart versioning for Casablanca 2.0.0->3.0.0
LF Helm repo status update
Helm Chart Limit reached - how to resolve for Casablanca?
Node Port Strategy
Dublin Planning
encouraging community to add requirements to OOM Requirements Gathering for Release Planning before next week
Dublin scoping will start next week in parallel with Casablanca development
Notes
I missed the Redis discussion but caught an action at the end. ACTION: Need to define what to do with Redis
OOM Casablanca - M3 API Freeze Milestone Checklist will be reviewed tomorrow. Please ensure that there are no non-Draft items older than 36hrs here: https://gerrit.onap.org/r/#/q/project:oom+and+status:open+and+age:36h
There are 2x 2 week sprints left until end of release. Please review the open items and pull in anything that you are able to complete. Two (2) sprints have been created - stories and tasks can be slotted here.
We have run into continuing issues with hitting the chart size limit - @Mike Elliott will set a meeting to discuss this to arrive at a plan to resolve. A bug has been raised and will be used to track the decision
Dublin planning will start next week - please add any new potential items to the Release planning page (Link in the Agenda above) so that they are visible for planning purposes
Node Port Strategy discussion is required - @Mike Elliott will set up for tomorrow if possible.
Story updates:
OOM-1123: Update all source code files with the Apache 2 License header - CasablancaClosed will be completed next week
MSB-286: Service endpoint annotation for Bus ControllerClosed @Doug Kedrosky will followup with @pradeep patel to confirm if this can still fit into Casablanca (not currently being worked per previous week update)
OOM-1228: GlusterFS configuration for ONAPClosed @Stephen Lanthier will complete the work shown as 'in progress'. ALL: Please review the remaining tasks and pick up any that you can. Work can be modeled from what Steve is completing currently.
OOM-1176: Create Charts for common MariaDB-GaleraClosed @Pramod Kumar Sharma is currently working to understand what changes to be made. @Mike Elliott will schedule a meeting with APPC for Thursday to discuss. SDNC should be a relatively simple extension once the APPC work is done. NOTE: Need to consider how data would be migrated from MySQL to MariaDB in production as part of the work (eg migration script). @Pramod Kumar Sharma will add a new task to cover this migration work.
OOM-1164: Create common mariadbClosed Will cover work for those moving to common MariaDB but not going to Galera in Casablanca. Anyone picking up a task should reach out to the relevant team (eg VID) to align on the requirements
OOM-1170: Create a new cnf file for the mariadb installation Closed Need to confirm who is now working this. @Doug Kedrosky will reach out to team to confirm
OOM-1146: Resource Limits for aafClosedResource Limit work is on track. Slow to get responses from teams so will complete with information proposed for now.
OOM-1232: Provide a Backup and Restore SolutionClosed Demo of DB backup and restore for next week
OOM-1242: Transfer helm chart ownership to remaining teamsClosed Not currently in progress - depends on the LF build jobs (which should be available this week). @Mike Elliott will potentially demo the LF work when available
OOM-1178: Create Charts for common Postres ClusterClosed Need to sync the work with @Jerome Doucerain team
OOM-1177: Create Charts for common CassandraClosed Hoping to complete in 2-3 days. New story to be added for Versioning of Helm Charts for Casablanca
OOM-1182: Implement Postgres ClusterClosed @Joanna Xu working with @Prateek Khosla to resolve the issue of failover when master not accessible. Working on a potential workaround/solution and currently hope to still complete within Casablanca