2020-03-11 VNFRQTS Weekly Project Meeting WEDNESDAY



Agenda:

Antitrust Policy Statement:  Meetings of the ONAP Project involve participation by industry competitors,  and it is the intention of the Project to conduct all of its activities in accordance  with applicable antitrust and competition laws. It is therefore extremely  important that attendees adhere to meeting agendas, and be aware of and not  participate in any activities that are prohibited under applicable U.S. state,  federal or foreign antitrust and competition laws. Examples of types of actions  that are prohibited at ONAP Project meetings and in connection with ONAP  Project activities are described in the The Linux Foundation Antitrust Policy. If  you have questions about these matters, please contact your company  counsel or Andrew Updegrove, of the firm of Gesmer Updegrove LLP, which  provides legal counsel to The Linux Foundation. Linux Foundation Antitrust Policy:  https://www.linuxfoundation.org/antitrust-policy



Attendees:

  1. @Trevor Lovett



No other attendees joined by 9:07 so I dropped the meeting. Relevant material is below:



#

Objective

How Achieved

Notes

Action items out

#

Objective

How Achieved

Notes

Action items out

1

Assemble/Welcome (5 min)







2

Review Recent Commits

Review Gerrit commits since last meeting

Review: 

https://gerrit.onap.org/r/q/project:%2522%255Evnfrqts/.*%2522+status:merged





3

Review Current Sprint Status



Review active sprint in JIRA



Sent email to @Amy Zwarico regarding security tickets in the current sprint, but slated for Guilin release to determine if these can be removed from the active sprint.

Created a new sprint carrying over unfinished sprint.  

Past Sprint Summary: 

https://jira.onap.org/secure/RapidBoard.jspa?rapidView=63&projectKey=VNFRQTS&view=reporting&chart=sprintRetrospective&sprint=1140



4

Plan New Sprint

Review latest stories/tasks/bugs in JIRA

New Sprint: https://jira.onap.org/secure/RapidBoard.jspa?rapidView=63&projectKey=VNFRQTS



Please reach out to @Trevor Lovett if you have new items you would like to address in this sprint.



Release Planning:

Frankfurt (new features)

M4: Closed (3/3)

RC0: 3/26

RC1: 4/9

RC2: 4/23

Sign-off: 5/7



 



Frankfurt Epics 





 

vnfrqts Project charter

vnfrqts Epics

vnfrqts User Stories



Goal is to have all changes in by 3/26 so we can create the Guilin branch and start work there as there are a number of tickets (VES, etc.) that are ready to be started.



6

Any other business











Meeting Recordings and Other Attachments

  File Modified
No files shared here yet.