[ExtAPI] Dublin M4 Code Freeze Milestone Checklist
The following items are expected to be completed for the project to Pass the M4 Code Freeze Milestone.
M4 Release Code Freeze Milestone overview is available in wiki.
Usage
Use the "Copy" option (available under the ..., top right of this page) to duplicate this template into your project wiki.
Fill out the Yes/No column
Provide link to evidence (when necessary)
Practice Area | Checkpoint | Yes/No | Evidences | How to? |
---|---|---|---|---|
Security | Has the Release Security/Vulnerability table been filled out in the protected Security Vulnerabilities wiki space? | Yes | ||
Are all Defects of priority Highest and High in status "Closed" in Jira? (this includes the Jira for Critical and Severe NexusIQ findings) | No | The only one is relative to complete the security table, which has been done, submitted | ||
Did the project achieve the enablement of transport level encryption on all interfaces and the option of disabling transport level encryption? | No | We still don't understand the process to get onap signed certificates | ||
Do all containers run as a non-root user and is documentation available for those containers that must run as root in order to enable ONAP features? | Yes | |||
Provide the "% Achieved" on the CII Best Practices program. | 95% | https://bestpractices.coreinfrastructure.org/en/projects/1771. | As documented in CII Badging Program, teams have to fill out CII Best Practices | |
Product Management | Have all JIRA Stories supporting the release use case been implemented? | No | For each JIRA story that are implemented in the current release, you have to setup in JIRA the JIRA fixVersion="Dublin Release" | |
List the Stories that will not be implemented in this current Release. | For each JIRA story that will not be implemented in the current Release, you have to setup in JIRA the JIRA fixVersion="El Alto Release" | |||
Are committed Sprint Backlog Stories been coded and marked as "Closed" in Jira? | NA | https://jira.onap.org/secure/RapidBoard.jspa?projectKey=EXTAPI&rapidView=43&view=planning | ||
Are all tasks associated with committed Sprint Backlog Stories been marked as "Closed" in Jira? | NA | https://jira.onap.org/secure/RapidBoard.jspa?projectKey=EXTAPI&rapidView=43&view=planning | ||
Is there any Critical and Severe level security vulnerabilities older than 60 days old in the third party libraries used within your project unaddressed? Nexus-IQ classifies level as the following:
which is complaint with CVSS V2.0 rating. | No | In the case critical known vulnerability are still showing in the report, fill out the Security/Vulnerability Threat Template - Beijing, Casablanca, Dublin in your project. | Ensure the Nexus-IQ report from “Jenkins CLM” shows 0 critical security vulnerability. Open the Nexus-IQ report for the details on each repo. | |
Release Management | Have all issues pertaining to FOSS been addressed? | Yes | ||
Have all findings from previous milestones been addressed? | Yes | For M2 and M3 Milestones, ensure all findings have been closed. | ||
Has the Project Team reviewed and understood the most recent license scan reports from the LF, for both (a) licenses within the codebase and (b) licenses for third-party build time dependencies? | Yes | |||
For both (a) and (b), have all high priority non-Project Licenses been either removed or escalated as likely exception requests? | Yes | |||
Development | Are all Defects of priority Highest and High in status "Closed" in Jira? | No | The only one is relative to complete the security table, which has been done, submitted | |
Has the Platform Maturity Table been updated with implementation Status at M4? | Yes | For each Release, there is a Platform Maturity table created for PTLs to record their goals and achievement at M4 (Example: Casablanca Release Platform Maturity) | ||
Has the project team reach the Automated Unit Test Code Coverage expectation? (Refer to artifacts available in Sonar) | Yes | 77,5% https://sonar.onap.org/dashboard?id=org.onap.externalapi-nbi%3Anbi-rest-services | ||
Is there any binaries (jar, war, tar, gz, gzip, zip files) in Gerrit project repository? | Yes | 2 csar files for testing purpose, 35Ko each | ||
Is there any pending commit request older than 36 hours in Gerrit? | No | Currently, only trying to solve a six days conflict | Gerrit Query: status:open label:verified -is:draft -label:Code-Review=-1 AND -label:Code-Review=-2 AND is:mergeable age:1week | |
Are all the Jenkins jobs successfully passed (verify + merge jobs)? | Yes | https://jenkins.onap.org/view/externalapi/job/externalapi-nbi-master-verify-java/ https://jenkins.onap.org/view/externalapi/job/externalapi-nbi-master-merge-java/ | ||
Have all OOM Staging Healtcheck related to your project passed? | Yes | https://jenkins.onap.org/view/externalapi/job/externalapi-nbi-master-csit-healthcheck/ | ||
Are all snapshot binaries available in Nexus-staging? | Yes | https://nexus.onap.org/content/repositories/snapshots/org/onap/externalapi-nbi/nbi-rest-services/ | ||
Do you have a clear plan to implement the Independent Versioning and Release Process by RC0? | Yes | Contact the upstream teams to make sure they will release their artifacts (in Nexus Release repo) so you can build by depending on these released artifacts by RC0. | ||
Integration and Testing | Have 100% of Continuous System Integration Testing (CSIT) Use Cases been implemented successfully in Jenkins? It should include at least 1 CSIT that will be run on Lab-xxx-OOM-Daily Jenkins Job | Yes | https://jenkins.onap.org/view/externalapi/job/externalapi-nbi-master-csit-healthcheck/ | |
Is there a Docker images available for your project deliverable? | Yes | |||
Has the project passed the Integration Sanity Tests? | Integration sanity tests in Dublin Release cover:
No test failure reported on http://onapci.org/grafana/d/8cGRqBOmz/daily-summary?orgId=1 No Integration Blocking Issue with no workaround: Dublin Release Integration Test Blocking Issues | |||
Has the project code successfully passed the Daily Build process? | Yes | https://jenkins.onap.org/view/externalapi/job/externalapi-nbi-master-release-version-java-daily/ | Goal is to ensure the latest project commit has not broken the Integration Daily Build | |
Doc | Does the project have a plan to finalise and close all remaining JIRA Documentation tickets? | Yes | Jira Query project != "Sandbox Project" AND project != "ONAP TSC" AND project != CI-Management AND (labels=Documentation OR project=Documentation) AND status != Closed ORDER BY fixVersion ASC, status DESC, priority DESC, updated DESC Jira Query (Bugs Only) project != "Sandbox Project" AND project != "ONAP TSC" AND project != CI-Management AND (labels = Documentation OR project = Documentation) AND issuetype= Bug AND fixversion = "Dublin Release" AND status != Closed ORDER BY issuetype DESC, fixVersion ASC, status DESC, priority DESC, updated DESC | |
Does the project team have a plan to complete all the Release related documents by RC1? | Yes |