This page is used to trace the develop tasks of the R12 general intent implementation requirement.
Project | Task Description | Owner | Status | Remark |
---|---|---|---|---|
UUI Intent Analysis Server | Enhance the intent CRUD implementation Flows. | zhen zhang | Open | 2023-4-6: Almost finish the coding work. |
Modeling | Update the Intent Model including the intent notification model. | zhen zhang | Open | 2023-4-6: Need to output a detailed document to describe the change. |
UUI Intent Analysis Server | Add AI model to support the intent translate feature. Use AI to translate the intent to service model. | Keguang He | Open | 2023-4-6: Will reuse the IBN NLP model to support the feature. under discussion with IBN team. |
UUI Intent Analysis Server | Support the intent notification flow. | Open | 2023-4-6: Not yet start. | |
UUI Intent Analysis Server | Support to get notification from DMaap to get the report of DCAE/Policy | Open | 2023-4-6: Not yet start. | |
UUI Intent Analysis | Support Not_Fulfilled report when SO returns fail during create service. | Open | 2023-4-6: Not yet start. also need to change the call to SO instead of to UUI-Server | |
DCAE | Support to sent event when the Bandwidth monitor fit the intent-not-fulfilled scenario. | Open | 2023-4-6: The design have been finished. the event model under defenition. | |
Policy | Support to sent event when the Bandwidth modify failed. | zhuguanyu | Open | 2023-4-6:Under Design. |
UUI Portal | Support to show the intent status column and show details action. | Open | 2023-4-6:Under Design. | |
ONAP installation& Test | ONAP installation & Test | Open | 2023-4-6: ONAP installed . Current face some issue with uui-server. |