Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 12 Next »


Overview

Project NameEnter the name of the project
Target Release NameLondon
Project Lifecycle StateMature. Refer to ONAP Charter, section 3.3 Project Lifecycle for further information
Participating Company AT&T, Nokia, Wipro, Huawei, DT, Capgemini

Scope

What is this release trying to address?

Release Focus

DCAE Focus for R12 

  • DCAE backlog reduction
  • Support TSC approved ONAP Usecases and Features (details below)
  • Address SECCOM identified vulnerability*
  • Alignment with TSC/SECCOM Global requirements & TSC/SECCOM Best Practice*
  • Continue AAF certificate dependency removal (for SVC mesh compaibility)* 
  • Code coverage improvements*

(*  - Stretchgoals)

London Usecases with DCAE impact

REQ#DCAE Commit StatusDCAE Impact AssessmentDCAE JIRA #
REQ-1378 - E2E Network Slicing use case enhancements for London release

YES

AI/ML MS for IBN based closed Loop in E2E Network Slicing

•    Mainstreaming the ml-prediction-ms (New mS introduction)
•    Support for multiple slices (sNSSAIs) in training and prediction modules
•    Use CPS instead of Config DB
•    Remove RAN Simulator dependency

Commitment from Kevin Tang sendil kumar Jaya kumar Ahila P /WIPRO  

DCAEGEN2-3067

London Features with DCAE Impact

REQ#DCAE Commit StatusDCAE Impact AssessmentDCAE JIRA #
REQ-1351 - External secure communication only via IngressNONo resource/support available from DCAE project; changes likely in OOM charts.

DCAEGEN2-3335

REQ-1349 - Removal of AAFStretch-goal

OOM-3068  (DCAE Svc template updates) - Jack Lucas 

DCAEGEN2-3095 /DCAEGEN2-3336 (RESTConf cert dependency removal) - Kedar Ambekar 

DCAEGEN2-3335 - VESOpenAPI - (question)

DCAEGEN2-3037 (EPIC) - Story DCAEGEN2-3095 /DCAEGEN2-3336 (RESTConf)


DCAEGEN2-3335 - VESOpenAPI



REQ-1376 - DMaaP Enhancements for L releaseNO

DMAAP BC removal support 

BC used mainly for BulkPM flow for Feed provisioning - need assessment on switching DFC/PM-Mapper to use non-secure endpoints.


London Spec with DCAE Impact

REQ#DCAE Commit StatusDCAE Impact AssessmentDCAE JIRA #
REQ-1379 - Improve DCAE PRH to handle Early PNF RegistrationsYES
  • Enable persistence for PRH reprocessesing
  • DCAE SDK dmaap-client enhancement to support native kafka interface

Commitment from Sangeeta Bellara / DT

DCAEGEN2-3312
DCAE MOD retirementYES

Retire MOD from ONAP/DCAE

  • OOM charts updates
  • Documentation

Commitment from Vijay Kumar / AT&T

DCAEGEN2-3278

PM-Mapper Improvement/Bug-fixesYES

Fix issues of duplicate events handling & DR retry

Commitment from Viresh Navalli / Vamshi Namilikonda Capgemini

DCAEGEN2-3315

DCAEGEN2-3313

NAYES

Sonarcoverage improvements for DCAE components

  • Heartbeat MS, VESCollector

Commitment from Vijay Kumar Tony Hansen AT&T


Sub-Jira under EPIC DCAEGEN2-3256

NAPENDING

DMAAP SDK standardization for DCAE Microservices (following components are using cambria client)

  • KPI-mS  (deferred from Kohn; need to be confirmed by Ahila P / Niranjana Y )
  • SON-Handler mS (deferred from Kohn; need to be confirmed by Ahila P / Niranjana Y )
  • RESTConf  (No resouce/support available from DCAE project)

DCAEGEN2-3030









London POC (DCAE impact)

REQ#DCAE Commit StatusDCAE Impact AssessmentDCAE JIRA #

REQ-1072 - Standardized logging fields 

REQ-1345 - Standardized logging fields - Python London release 

NONo resources for POCNA

Best Practices/GLOBAL Requirements

REQ#DCAE Commit StatusDCAE Impact AssesmentDCAE JIRA #

REQ-443 - CONTINUATION OF CII BADGING SCORE IMPROVEMENTS FOR SILVER LEVEL

Global-REQ 

YES

DCAE passed silver badging; Gold badging improvements dependent on LF wide policy/infra updates.

(No new impact for DCAE)

NA

REQ-1211- CONTINUATION OF PACKAGES UPGRADES IN DIRECT DEPENDENCIES

Global-REQ

Stretch-goal

London DCAE 

Commitment: Kedar Ambekar / DT Team  (TCAGEN2/RESTConf/PM-Mapper, DataFileCollector, VESMapper, SDK, VES-OpenAPI manager)

Following are OPEN  (pending resource/commitment)

DCAEGEN2-3318

REQ-437 - COMPLETION OF PYTHON LANGUAGE UPDATE (v2.7 → v3.8)

Global-REQ

YES

Existing DCAE python components are already compliant; New mS (ml-prediction-mS) will also meet this requirement when delivered.

Covered under REQ-1378 (Commitment from Kevin Tang Ahila P /WIPRO  )

NA

REQ-438 - COMPLETION OF JAVA LANGUAGE UPDATE (v8 → v11)

Global-REQ

YES

Complaint with DCAEMOD deprecation.

Java17 upgrade pilot targetted for PM-Mapper in London (supported by Kedar Ambekar/DT Team)

NA
REQ-432 - IPv4/IPv6 dual stack support in ONAPYES

Enhance ONAP common-service template - add IPv4/IPv6 support

(No new impact for DCAE)

OOM-2749 

REQ-441/REQ-1070 - LOGS MANAGEMENT - PHASE 1: COMMON PLACE FOR DATA - London RELEASE

Global-REQ

YES

New mS (ml-prediction-mS) will be complaint to the requirement. All other DCAE mS area already complaint STDOUT logging


Covered under REQ-1378 (Commitment from Kevin Tang Ahila P /WIPRO  )

Tracked under DCAEGEN2-3067

REQ-1073 - Using basic image from Integration  

YES

(No new impact for DCAE in London release)

NA

REQ-1072 - Standardized logging fields REQ-1341 - Standardized logging fields - Java London release 

Stretch-goal

Will need updates to several DCAE java component - no resource

(only vescollector updates committed by AT&T)

REQ-1342 - Retirement of unmaintained repos YES

DCAE MOD will be retired in London release

Commitment from Vijay Kumar / AT&T

DCAEGEN2-3278





Best Practices

REQ#DCAE Commit StatusDCAE Impact AssesmentDCAE JIRA #

REQ-396 - Clearly split ONAP code and use case code

YES

No new impact; already compliant

NA

REQ-399 - ONAP Projects dealing with GUI must provide GUI test suitesNO

DL Admin is only DCAE component with UI

No resource/commitment

NA
REQ-1073 - Using basic image from IntegrationYESNo new impact; already compliantNA
REQ-1346 - Software BOMsYESNo new impact; already compliantNA



Note: The above commitment should be consistent with London Impact View per Component at M2.

New Services/Components

Following new services will be delivered under E2E Slicing usecase for IBN based closed Loop support.


Retirement/Deprecation


      DCAE MOD

DCAE MOD was introduced in Frankfurt release to address following requirements:

    1. Simplified and streamlined onboarding for DCAE components/microservice and distribute the deployment artifact with DCAE-Core Platform (Cloudify)
    2. Provide Common Catalog for reusable DCAE microservices for Designer to leverage
    3. Enable automated onboarding for ML microservices from Acumos. 

With DCAE platform transformation feature, requirement #1 and #2 are less critical as the onboarding/deployment are easily managed through Helm-Charts and catalog supported through Chartmuseum (or any other registry)/With Also with Acumos project archived under LF (end of 2021), DCAE team will be assessing the need for continuation/support of DCAE MOD going forward.  

Note: Certain MOD components are on java8 due to upstream dependency with Apache/Nifi project on java8 and have SECCOM exception currently.

Update 07/19/22

Following DCAE Team meeting discussion and ARC reviews, DCAE-MOD has been identified for retirement with London release. Official communication sent to ONAP DL's - https://lists.onap.org/g/onap-tsc/topic/dcae_mod_eol_with_london/92490689


Platform Maturity

 Platform Maturity (i.e., S3P items)  London Release Platform Maturity


 Green color → Target level ( details see Platform Maturity below)

      • Performance:  Level 1
      • Stability: Level 2
      • Resiliency: Level 2
      • Security: Level 1+
      • Scalability: Level 1
      • Manageability: Level 1+
      • Usability: Level 1+             

Minimum Viable Product

As DCAE transformation is underway, two different deployment options will be available. The MVP of DCAE will vary based on deployment choice and will include the necessary subcomponents supporting the primary objectives: meeting platform maturity goals and supporting the use cases.


Helm Deployment (dcaegen2-services)

    •   VESCollector
    •   TCA-gen2
    •   PRH
    •   HV_VES


  

Functionalities

List the functionalities that this release is committing to deliver by providing a link to JIRA Epics and Stories. In the JIRA Priority field, specify the priority (either High, Medium, Low). The priority will be used in case de-scoping is required. Don't assign High priority to all functionalities.

Epics

key summary type created updated due assignee reporter priority status resolution
Loading...
Refresh

Stories

key summary type created updated due assignee reporter priority status resolution
Loading...
Refresh

Longer term roadmap

With DCAE Helm transformation initiate completed, achieved the major goal on platform simplification. As ONAP progresses for supporting new usecase, will assess them for support.

Following are some initiatives under consideration

    • Policy/CLAMP: Continue integration for Control Loop design for Helm-based deployment of DCAE Services*
    • Prometheus Integration
    • TICK/ELK Integration

Release Deliverables

Indicate the outcome (Executable, Source Code, Library, API description, Tool, Documentation, Release Note...) of this release.

Deliverable NameDeliverable Description
policy side-carSourceCode/Docker image
dcae-healthcheckSourceCode/Docker image
dcae-modSourceCode/jar/Docker image/Documentation

VES Collector

SourceCode/Docker image/helm charts

HV_VES CollectorSourceCode/jar/Docker image/helm charts
PRHSourceCode/jar/Docker image/helm charts
TCA-GEN2SourceCode/jar/Docker image/helm charts
DFCSourceCode/Docker image/helm charts
RESTConfSourceCode/Docker image/helm charts
PM-MAPPERSourceCode/Docker image/helm charts
VES-MAPPERSourceCode/Docker image/helm charts

DL Components (DES,

DL-ADMIN, DL-FEEDER)

SourceCode/Docker image/helm charts
SLICE ANALYSISSourceCode/Docker image/helm charts

KPI-MS

SourceCode/Docker image/helm charts
HEARTBEAT MSSourceCode/Docker image/helm charts
SON-HANDLER MSSourceCode/Docker image/helm charts
PMSHSourceCode/Docker image/helm charts
ML/Prediction Ms SourceCode/Docker image/helm charts

Note: Only default platform components and bootstrapped MS is listed on table above. DCAE also include dynamic service components deployed based on usecases. For a complete set of available DCAE MS - refer https://docs.onap.org/projects/onap-dcaegen2/en/latest/sections/release-notes.html#deliverables


Sub-Components

List all sub-components part of this release. Activities related to sub-components must be in sync with the overall release.

Sub-components are repositories and are consolidated in a single centralized place. Edit the Resources and Repositories (Deprecated) in the centralized page.


ONAP Dependencies

List the other ONAP projects you depend on.


DCAE depends on the the following components as part of the general ONAP architecture:

    • AAI: DCAE MS retrieves and updates VNF data from/to AAI
    • DMaaP: Message bus for communication with other components in the solution
    • Policy/CLAMP - Policy - For managing application configuration policy. 
    • OOF - For SON handler support

Architecture

High level architecture diagram

At that stage within the Release, the team is expected to provide more Architecture details describing how the functional modules are interacting.

Indicate where your project fit within the Amsterdam architecture diagram_1.0.0.pptx.


 DCAE Interfaces


Platform Maturity


London Release Platform Maturity


Refering to 2017-06-28 CII badging for ONAP.pptx and Platform Maturity Requirements (aka Carrier Grade), fill out the table below by indicating the actual level , the targeted level for the current release and the evidences on how you plan to achieve the targeted level.

AreaActual LevelTargeted Level for current ReleaseHow, EvidencesComments
Performance11
    • Level 0: no performance testing done
    • Level 1: baseline performance criteria identified and measured  (such as response time, transaction/message rate, latency, footprint, etc. to be defined on per component)
    • Level 2: performance improvement plan created 
    • Level 3: performance improvement plan implemented for 1 release (improvement measured for equivalent functionality & equivalent hardware)
Stability2

2




    • Level 0: none beyond release requirements
    • Level 1: 72 hour component-level soak test (random test transactions with 80% code coverage; steady load)
    • Level 2: 72 hour platform-level soak test (random test transactions with 80% code coverage; steady load)
    • Level 3: track record over 6 months of reduced defect rate
Resiliency22
    • 0 – none
    • 1 – manual failure and recovery (< 30 minutes)
    • 2 – automated detection and recovery (single site)
    • 3 – automated detection and recovery (geo redundancy)
Security1

1+  



    • Level 0: None
    • Level 1: CII Passing badge
      • Including no critical and high known vulnerabilities > 60 days old
    • Level 2: CII Silver badge, plus:
      • All internal/external system communications shall be able to be encrypted.
      • All internal/external service calls shall have common role-based access control and authorization using CADI framework.
    • Level 3: CII Gold badge 
Scalability1

1



    • Level 0: no ability to scale
    • Level 1: supports single site horizontal scale out and scale in, independent of other components
    • Level 2: supports geographic scaling, independent of other components
    • Level 3: support scaling (interoperability) across multiple ONAP instances
Manageability1

1+  (Except logging, all other requirements are met)



    • Level 1:
    • All ONAP components will use a single logging system.
    • Instantiation of a simple ONAP system should be accomplished in <1 hour with a minimal footprint
    • Level 2:
      • A component can be independently upgraded without impacting operation interacting components
      • Component configuration to be externalized in a common fashion across ONAP projects
      • All application logging to adhere to ONAP Application Logging Specification v1.2
      • Implement guidelines for a minimal container footprint
    • Level 3
      • Transaction tracing across components
Usability1

1+



    • Level 1:
      • User guide created
      • Deployment documentation
      • API documentation
      • Adherence to coding guidelines
    • Level 2:
    • Level 3
      • Consistent UI across ONAP projects
      • Usability testing conducted
      • API Documentation
    • Level 4


  • API Incoming Dependencies

List the API this project is expecting from other projects. Prior to Release Planning review, Team Leads must agreed on the date by which the API will be fully defined. The API Delivery date must not be later than the release API Freeze date.

Prior to the delivery date, it is a good practice to organize an API review with the API consumers.

API NameAPI DescriptionAPI Definition DateAPI Delivery dateAPI Definition link (i.e.swagger)
Policy EngineAPI for retrieving configuration policy updates via Policy SidecarCurrently AvailableCurrently AvailableNA
Policy (PDP) API to push DCAE MS configuration/policy modelsCurrently AvailableCurrently Available
A&AIAPI invoked for information enhancementsCurrently AvailableCurrently Available
DMaaP Message RouterAPI for topic publish /subscribeCurrently AvailableCurrently Available
DMaaP Bus ControllerDMaaP Bus Controller is a part of DMaaP that provides topic provisioning; this is the API for topic provisioning.Currently AvailableCurrently Available
 OOF

 PCI Optimization API http://{OOF-host}:{port}/api/oof/v1/pci

 http://{pcims-host}:{port}/callbackUrl Call back URL for SON-MS (to provide PCI optimization results)

 Currently Available Currently Available
 ConfigDB

http://{ConfigDB-host/IP}:{port}/SDNCConfigDBAPI/getNbrList/{cellId}/{ts} (Get neighbor list for  a cell Id)

http://{ConfigDB-host/IP}:{port}/SDNCConfigDBAPI/getPnfName/{cellId}/{ts} (Get the PNF name for a cell Id)
 Currently AvailableCurrently AvailableThis will be replaced with CPS for Jakarta
CPSUsed by SON-handler and Slice-Analysis MSCurrently AvailableCurrently Available
  • API Outgoing Dependencies

API this project is delivering to other projects.

API NameAPI DescriptionAPI Definition DateAPI Delivery dateAPI Definition link (i.e.swagger)
VES CollectorAPI for VNFs to send VES data Currently Available
No change for this release
HealthcheckAPI for querying DCAE component healthcheck Currently AvailableR4No change for this release
Data Extraction Service (DES)API for data retrieval and simple computation from DL-Handler maintained storages (For R8, this will be used by DCAE components such Slice-Analyis MS) and UUICurrently AvailableR8No change for this release
PMSH API support for Subscription/Filters/Measurement group management Currently AvailableR10

No change for this release

https://git.onap.org/dcaegen2/tree/docs/sections/apis/pmsh_swagger.json


SliceAnalysis MsAPI support for data aggregation based on NSI/NSSI; this will be consumed by OOFCurrently AvailableR10

No change for this release

https://git.onap.org/dcaegen2/tree/docs/sections/apis/swagger_slice_analysis.json

https://wiki.onap.org/download/attachments/117740396/slice-analysis-swagger.yaml?version=1&modificationDate=1640159785000&api=v2






  • Third Party Products Dependencies

Third Party Products mean products that are mandatory to provide services for your components. Development of new functionality in third party product may or not be expected. List the Third Party Products (OpenStack, ODL, RabbitMQ, ElasticSearch,Crystal Reports, ...).

NameDescriptionVersion



In case there are specific dependencies  (Centos 7 vs Ubuntu 16. Etc.) list them as well.

  • Gaps

This section is used to document a limitation on a functionality or platform support. We are currently aware of this limitation and it will be delivered in a future Release. List identified release gaps (if any), and its impact.

Gaps identifiedImpact


  • Known Defects and Issues

Provide a link toward the list of all known project bugs.

key summary type created updated due assignee reporter priority status resolution
Loading...
Refresh

  • Risks

List the risks identified for this release along with the plan to prevent the risk to occur (mitigation) and the plan of action in the case the risk would materialized (contingency).

Risk identifiedMitigation PlanContingency Plan
Documented under London Risks

  • Resources

Please see the INFO.yaml files associated with each repo as the authoritative sources of information. https://gerrit.onap.org/r/admin/repos/q/filter:dcae

  • Release Milestone

The milestones are defined at the Release Planning: London and all the supporting project agreed to comply with these dates.


  • Team Internal Milestone

This section is optional and may be used to document internal milestones within a project team or multiple project teams. For instance, in the case the team has made agreement with other team to deliver some artifacts on a certain date that are not in the release milestone, it is erecommended to provide these agreements and dates in this section.

It is not expected to have a detailed project plan.

Date to be completed bySprint#No of days Deliverable 
Key dates for London release - Release Planning: London
M2DCAE London Sprint 1 (Planning)
  • Finalize DCAE scope and committment
  • API definition formalized and shared with impacted teams
M2-M3DCAE London Sprint 2 (Development)
  • 50% or more of Functional delivery completed
  • Atleast 60% of release/compliance (coverage & security)
  • Integration test plan completed
  • CSIT/automated test delivery
  • SDK version to be baselined and released
  • Documentation repo updates (API updates & new MS/component) - London Documentation
M3 DCAE London Sprint 3 (Code Freeze)
  • All code intended for release MUST be submitted into gerrit
  • Minimum 80% code coverage
  • 100% of release/compliance (Global Requirement & Best-Practice) 
  • Validate deployment/integration with ONAP/DCAE deploy
  • Update OOM chart/documentation to reflect correct version
  • Documentation update for deployment/configuration/architecture/logging
M4DCAE London Sprint 4  (Container Release/artifact)

Finalize containers/jars for release and submit patch to OOM for revisions

RCIntegration/Sign-Off
  • Fix Integration blockers and high priorty issue
  • Demo for new components introduced
  • Pair-wise testing
  • Branching
  • Documentation, Training


      • Highlight the team contributions to the specific document related to he project (Config guide, installation guide...).
      • Highlight the team contributions to the overall Release Documentation and training asset
      • High level list of documentation, training and tutorials necessary to understand the release capabilities, configuration and operation.
      • Documentation includes items such as:
        • Installation instructions
        • Configuration instructions
        • Developer guide
        • End User guide
        • Admin guide

           London Documentation

Other Information

    • Vendor Neutral

If this project is coming from an existing proprietary codebase, ensure that all proprietary trademarks, logos, product names, etc. have been removed. All ONAP deliverables must comply with this rule and be agnostic of any proprietary symbols.

    • Free and Open Source Software

FOSS activities are critical to the delivery of the whole ONAP initiative. The information may not be fully available at Release Planning, however to avoid late refactoring, it is critical to accomplish this task as early as possible. List all third party Free and Open Source Software used within the release and provide License type (BSD, MIT, Apache, GNU GPL,... ). In the case non Apache License are found inform immediately the TSC and the Release Manager and document your reasoning on why you believe we can use a non Apache version 2 license.

Each project must edit its project table available at Project FOSS.


Charter Compliance

The project team comply with the ONAP TSC Charter OBSOLETE 7 1 CLEAN.pdf.


  • No labels