Release Schedule
Revision: r2
Activity Log
Date | Rev | Event or Update | Milestones Affected |
---|---|---|---|
12/08/22 | r2 | The TSC rescheduled M1 to Dec 15 due to lack of progress on release management tasks. | M1 |
11/10/22 | r1 | The TSC slipped the date for Kohn Sign Off to Dec 1. To prevent the Kohn and London schedules from overlapping, the TSC agreed to push out M1 by one week. | M1 |
09/22/22 | Schedule proposal approved by the TSC | All | |
09/15/22 | First draft posted | All |