The ONAP community chose to re-name the "K" release (originally "Kyoto") in honor of the late CNCF Executive Director, visionary, entrepreneur, and open source advocate and pioneer, Dan Kohn, who passed in the fall of 2020. More information about Dan here.
Release Schedule
Revision: r5
Activity Log
Date | Rev | Event or Update | Milestones Affected |
---|---|---|---|
09/01/22 | r5 | The TSC pushed M3 and M4 out by one week, each to Sept 8 and Sept 22, respectively. Other milestones remain the same. Also added the Thanksgiving holiday. | M3, M4 |
07/21/22 | r4 | The TSC conditionally approved M2. | M2 |
07/14/22 | r4 | The TSC pushed M2 out one week to July 21. Also updated the sign off date shown for the Jakarta release to the actual release date (June 30). | M2 |
06/23/22 | r3 | The TSC conditionally approved M1 | M1 |
06/09/22 | r3 | The TSC approved moving M1 to June 23. | M1 |
06/02/22 | r2 | The TSC approved moving M1 to June 9 (May 24 proposal) | M1 |
05/24/22 | r2 | Updated May 19 proposal based on feedback from PTLs at May 23 PTL meeting. Moved M2 from June 30 to July 14. Still requires TSC approval. | M2 |
05/19/22 | r1 | Identified a conflict between M1 and Ascension Day on May 26, due to Ascension Day not being on the original schedule. Proposed moving M1 to June 9 and M2 to June 30. Need to review with PTLs and then vote in TSC on June 2. Added Ascension Day. | M1, M2 |
03/31/22 | initial approved | TSC approved Kohn schedule | All |
03/10/22 | First draft posted | All |