DCAE being large project (41 components in Guilin) need more resource and time for complaince with non-functional requirements. We made significant progress this release, however due to number of components impacted, adopting phased approach.
DCAE platform also has upstream dependency (NiFi for MOD & Cloudify ) - some of the ONAP NFR requires work in upstream community.
Schedule impact
N/A
Recovery plan
Continue phased approach in coming releases based on commitment from the community.
For upstream dependency : Followup with upstream community and/or determine alternate solution which might involve DCAE ARC impact
Milestone schedule change
N/A
Risk
The risk is that the aforementioned DCAE components will not be able to meet Guilin NFR