Attendees:
- Catherine
- Sylvain
- David
- Arpit
- Shubra
- Andy
- Eric
- Morgan
Notes:
- Agreed to pursue Azure and VEXX solutions in parallel. Community can decide on final solution at a later date.
Team (administrators of account)
Plan/Timeline:
- Create Azure account
- Plan for Azure rollout (Andy's team - Sept 27)
- Negotiate w Microsoft (Arpit/GB)
- CI integration (community)
- Team provides plan/schedule for CI integration to TSC (Morgan/Sylvain)
- Followup meeting for current attendees.week of Oct 7 (David to arrange)
- VEXX
- Andy to follow up with Sylvain/Morgan on configuration details
- Initial setup available by Oct 4 (Andy's team)
- Evaluation
- Team creates evaluation plan (Oct 25)
- Team (above) presents initial evaluation results/cost to TSC (Dec 12 ?)
- Team presents final results/cost and makes recommendation to TSC on Jan 23
- Dismantle other solution