Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 4 Next »

Attendees:

  • Catherine
  • Sylvain
  • David
  • Arpit
  • Shubra
  • Andy
  • Eric
  • Morgan

Notes:

  • Agreed to pursue Azure and VEXX solutions in parallel.  Community  can decide on final solution at a later date.

Team (administrators of account)

Plan/Timeline:

  • Create Azure account 
    • Plan for Azure rollout (Andy's team - Sept 27)
    • Negotiate w Microsoft (Arpit/GB)
    • CI integration (community)
      • Team provides plan/schedule for CI integration to TSC (Morgan/Sylvain)
  • VEXX
    • Andy to follow up with Sylvain/Morgan on configuration details
    • Initial setup available by Oct 4 (Andy's team)
  • Evaluation
    • Team creates evaluation plan (Oct 25)
    • Team (above) presents initial evaluation results/cost to TSC (Dec 12 ?)
    • Team presents final results/cost and makes recommendation to TSC on Jan 23
    • Dismantle other solution
  • No labels