Use this page to record your review of the Dublin release - the PTLs will review and summarize prior to review at the TSC meeting after  


  • RC0 attempt to integrate and test was not successful - no CI/CD and a large set of changes integrated at once negatively impacted system stability
  • Early start of integration testing helps issue resolution earlier than the tail end of the release
  • Project team engaging in the integration process accelerated the process of integration - zoom shared debug sessions (much faster than jira)
  • Addition of OJSI Jira has been useful to create more focus on security issues - vulnerabilities are easier to track
    • Nexus vulnerabilities analysis still is very difficult - need some innovation
  • AAF underestimated the difficulty of changing the service locator
    • Infrastructure changes need to start very early in the release 
    • Plan for backward compatibility up front
  • SECCOM TTL for test certificates doesn't impact the security - probably longer than a year
  • OOM verify job was very helpful - finding defects before merged into the charts
  • Need to do installation testing in other places than just Windriver to catch environment assumptions
    • Diverse lab test envs (Orange) was helpful
    • Many versions of OpenStack
  • Need to start with keystone V3 install in El Alto - installation jobs will be changed (authentication)
  • Lack of available lab resources   
  • Need devops CI/CD to get more end2end visibility from developer perspective
    • 72 hr (longevity) stability runs should be reviewed by the PTLs - monthly review in the PTL meeting 
  • Delay in Dublin - issues not found until the very end
    • Testing started earlier in the release
    • Functional deployments exposed more defects and happen late in the release
      • Intersystem testing should start sooner
      • Instantiate vFW as a step in the CI/CD process - fully automated testing and very stable
    • Requirements came too late in the process
    • Need to begin the testing of Functional requirements earlier
    • Teams need to be transparent into the actual status of the milestones - example: projects marked as code complete were not complete
  • Retrospectives best done in person
  • Off-line installation finding new issues - could be done earlier to find issues