Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 4 Next »

DRAFT PROPOSAL FOR COMMENTS

The following items are expected to be completed for the project to Pass  Release Sign-Off Milestone.

Release Sign-Off Milestone overview is available in wiki.


Usage

  1. Use the "Copy" and "Move" options (available under the ..., top right of this page) to duplicate this template into your project wiki.
  2. Fill out the Yes/No column
  3. Provide link to evidence (when necessary)
Practice AreaCheckpointYes/NoEvidencesHow to?
Product ManagementAre committed Product Backlog Stories been coded and marked as "Closed" in Jira?Yes

key summary type created updated due assignee reporter priority status resolution
Loading...
Refresh


Are all tasks associated with committed Product Backlog Stories been marked as "Closed" in Jira?No

key summary type created updated due assignee reporter priority status resolution
Loading...
Refresh

The 2 tasks left are:

  • release note - waiting to be merged
  • adding Jim Baker to CII Badging - only michaelcan do that


Provide the project features list under the form of a bulleted list.YesSee Release Notes

Summarize any functionalities that were planned at Release planning and not delivered at Release Sign-Off

Yes

key summary type created updated due assignee reporter priority status resolution
Loading...
Refresh


Release ManagementHave all issues pertaining to FOSS been addressed?Yes

Have all findings from previous milestones been addressed?Yes

DevelopmentAre all the Jenkins jobs successfully passed (verify + merge jobs)?

https://jenkins.onap.org/view/Merge-Jobs/
Are all binaries available in Nexus Release repository?
Provide link to evidence
Are all Docker images available In Nexus?
Provide link to evidence
Are the Java and Docker manifest updated with the same version as in Nexus Release repository?


OOM to Tag Release + Version in Helm Chart


Integration and Testing

Have all CSIT Use Cases (created by each project team) passed?


It should include at least 1 CSIT that will be run on


Lab-xxx-OOM-Daily Jenkins Job


Provide link to evidenceGoal is to incease our confidence the latest commit did not break the major functionality. Jenkins CSIT Jobs
Has the project code successfully passed the Daily Build process?
Provide link to evidenceGoal is to ensure the latest project commit has not broken the Integration Daily Build 
Has the project passed the Integration Sanity Tests

Integration sanity tests in Dublin Release cover:

  • ONAP deployment
  • All components health check
  • VNF onboarding and service creation for vFW use case
  • Model distribution for vFW
  • vFW instantiation
  • vFW closed loop
  • vFW deletion

No test failure reported on http://onapci.org/grafana/d/8cGRqBOmz/daily-summary?orgId=1

No Integration Blocking Issue with no workaround: Dublin Release Integration Test Blocking Issues

Has the project done the integration testing with related dependent projects?




Documentation

Has your team completed (reviewed, submitted and cherry picked) all documentation planned for the Dublin Release?

  1. Release Notes
  2. Project Documentation
  3. No remaining Documentation tickets

Provide Link to ReadTheDocs Release Notes

Provide Link to ReadTheDocs Project Documentation

JIRA Query

project != "Sandbox Project" AND project != "ONAP TSC" AND project != CI-Management AND (labels=Documentation OR project=Documentation) AND status != Closed ORDER BY fixVersion ASC, status DESC, priority DESC, updated DESC


  • No labels